A customer is buying 10 new Power 720 servers and will integrate them into their existing data center which also has two Power 595s and five Power 750s, taking the total number of systems to 17. All currently installed systems are managed by a single H

题目

A customer is buying 10 new Power 720 servers and will integrate them into their existing data center which also has two Power 595s and five Power 750s, taking the total number of systems to 17. All currently installed systems are managed by a single HMC.All the machines will have dual VIO Servers for redundancy, and 10 client LPARs. How can they manage the new machines for the least cost?()

  • A、Purchase a second HMC and use this to manage the new servers.
  • B、Connect all of the new servers to the existing private HMC network.
  • C、Configure a second private network on their existing HMC for the new servers.
  • D、Connect 9 of the new servers to the existing HMC and use Integrated Virtualization Manager on the 10th.

相似考题
参考答案和解析
正确答案:B
更多“A customer is buying 10 new Power 720 servers and will integrate them into their existing data center which also has two Power 595s and five Power 750s, taking the total number of systems to 17. All currently installed systems are managed by a single HM”相关问题
  • 第1题:

    A customer has an IBM System Storage Enterprise Storage Server and several EMC CX3 systems installed in a data center, attached to IBM System p servers. As a step toward data consolidation, they intend to put all data on a new DS8700.  What would be the most important data migration factors to consider()

    • A、sector size and the amount of production data
    • B、existing RAID levels and the disk drive speed
    • C、sector size and existing RAID levels
    • D、amount of production data and the disk drive speed

    正确答案:D

  • 第2题:

    A customer has an entry level Power System that is currently partitioned and managed by a Hardware Management Console (HMC). For operational reasons, it must be disconnected from the HMC and configured as a new development system.  How should the customer proceed to implement PowerVM Express and Integrated Virtualization Manager (IVM) on this Power System? ()

    • A、 Install a VIO server as an additional partition and DLPAR the resources from the existing partition to the VIO server.
    • B、 Create a service partition and install a VIO server. This will automatically move resources to the VIO server on reboot of the managed system.
    • C、 Delete all the existing LPARs, create a new LPAR and assign all the system resources to this LPAR and then install the VIO server on this LPAR.
    • D、 Reset the machine to Manufacturing Default Configuration and install the VIO server on the resulting partition created, which will own all system resources.

    正确答案:D

  • 第3题:

    A customer wants to run VMWare ESX on an x445 with a large number of virtual machines running Windows 2003 Server as a Disaster Recovery (DR) Site for the production environment.  Which of the following questions would most impact the memory configuration?()

    • A、What version of VMWare ESX Server is being considered?
    • B、Do the systems currently use Double Data Rate (DDR) memory?
    • C、What is the total number of processors installed in the production systems?
    • D、What is the total amount of memory currently being used across all the production systems?

    正确答案:D

  • 第4题:

    A customer has 5 older POWER5 systems and they want to consolidate them onto a POWER6 system. What information is important to analyze when deciding how to design the new machine using the System Planning Tool?()

    • A、 vmstat and iostat data from the older machines 
    • B、 The number of CPUs that were installed in the original machines 
    • C、 Data from Workload Estimator (WLE) and IBM Performance Management (PM) 
    • D、 Performance data that is collected from the new system after it has been put into production

    正确答案:C

  • 第5题:

    A customer has a new Power 720 with PowerVM Standard Edition.  They plan to migrate their single-partition POWER5 550 to the new Power 720.   How can the customer migrate from the POWER5 550 to the Power 720 with minimal effort and down time?()

    • A、Perform Live Partition Mobility between the two systems.
    • B、Move the boot disks from the old system to the new system.
    • C、Use Tivoli Storage Manager to back up the POWER5 550 and restore on the Power 720.
    • D、Upgrade AIX to the latest level on the POWER5 550 and clone using the mksysb command.

    正确答案:D

  • 第6题:

    A customer currently has five partitioned POWER4 systems and is adding new systems.  When the pSeries technical specialist introduces the first p5 system with CoD into this environment, how should the HMC be handled?()

    • A、Order a new HMC to support the p5 system.
    • B、Attach the new p5 system to the existing HMC.
    • C、Upgrade the existing HMC to accommodate both the POWER4 and p5 systems.
    • D、Do nothing.  This system does not require an HMC.

    正确答案:A

  • 第7题:

    What is an advantage of using an HMC rather than IVM for system management?()

    • A、Support for a single VIO Server environment
    • B、Adapters can be dedicated or virtual for each LPAR environment
    • C、Interfaces with Systems Director to manage the Power Systems servers
    • D、Supports multiple Power Systems servers from a single point of control

    正确答案:D

  • 第8题:

    A Power 770 customer needs to add additional I/O adapters.  There is no room for the cards, so an I/O drawer must be added. What resource will help identify supported I/O drawers and the maximum number of drawers permitted per loop?()

    • A、I/O Planning Guide
    • B、Power Systems data sheet
    • C、Power Systems Facts and Features
    • D、Run FLRT to recommend I/O features

    正确答案:C

  • 第9题:

    单选题
    Company.com has recently received a new p5-570 in the data center and wants to Micro-Partition the server. The customer already has an existing HMC connected to a p690. Which of the following actions should the technical specialist take?()
    A

    Order a POWER5 HMC

    B

    Connect to the existing HMC

    C

    Install an 8-port asynchronous card in the managed server to connect to the existing HMC

    D

    Install an additional network card to the existing HMC and connect to the POWER5 service processor


    正确答案: B
    解析: 暂无解析

  • 第10题:

    单选题
    A customer has the following equipment installed in their data center:  (1)an IBM BladeCenter H chassis (2)two power supplies  (3)six HS22V blades (4)three Nortel 1/10 GB ESMs The retail customer purchased a new HX5 with MAX5.  Which of the following must be added to install the HX5 with MAX5?()
    A

    Two additional power supplies

    B

    Fibre Channel (FC) switches and SAN storage

    C

    A Nortel 1/10 GB ESM

    D

    SSD for the HX5


    正确答案: D
    解析: 暂无解析

  • 第11题:

    单选题
    A customer has a mixed environment of AIX on POWER4 and POWER5, and x86 based systems running a supported distribution of Linux. There is a total of 7 partitions and three standalone x86 servers. The customer wants to consolidate their applications using a single 4-core POWER6 server.  What is the minimum PowerVM edition that supports the customer requirement?()
    A

     PowerVM Lx86

    B

     PowerVM Express Edition

    C

     PowerVM Standard Edition

    D

     PowerVM Enterprise Edition


    正确答案: B
    解析: 暂无解析

  • 第12题:

    单选题
    A customer’s data center has all POWER4+ systems, and they plan to add three new p5-570 systems.  They will be purchasing a new 7310-CR2 HMC to support the POWER5 systems.  What is a key requirement that they need to plan for with the new HMC?()
    A

    A desk, as it not rack mountable

    B

    Ethernet connections to the POWER5 systems

    C

    Serial connections to the POWER5 systems

    D

    USB connections for the keyboard and mouse


    正确答案: A
    解析: 暂无解析

  • 第13题:

    A data center has had a power outage. Which of the following should the administrator do FIRST once the power is restored? ()

    • A、 Identify which systems are the most critical and bring them up by level of importance.
    • B、 Retrieve the latest backup tapes for immediate system restore using the GFS rotation.
    • C、 Identify the least critical systems and then power those systems on first.
    • D、 Determine the cause of the power outage and install UPS systems to prevent its reoccurrence.

    正确答案:A

  • 第14题:

    A customer has a combination of fifteen Windows file servers with direct attached storage and three Power Systems with AIX database servers SAN attached to a DS4700.  They would like to upgrade and plan for 40 TB capacity.  The customer needs to move to a more scalable storage system to include all servers.Which of the following would be most appropriate to ask first?()

    • A、What are the plans for Disaster Recovery? 
    • B、What are the plans for data migration? 
    • C、Would iSCSI meet your needs? 
    • D、How much space is available in the current storage systems?

    正确答案:B

  • 第15题:

    A customer has several single partition POWER5 and POWER6 processor-based systems housed in regional data centers and wants to consolidate into a single Power 770. They must minimize overall cost and the number of adapters, while ensuring a reliable infrastructure. Which solution addresses the customer requirements?()

    • A、Move the storage into a common SAN and virtualize the I/O using a single VIO Server with dual NIC connectors and dual HBAs
    • B、Move the existing physical network and storage adapters to the new system and virtualize the I/O using a  single VIO Server.
    • C、Move the storage into a common SAN and virtualize the I/O using dual VIO Servers, each with dual NIC  connectors and dual HBAs.
    • D、Move the storage into a common SAN and virtualize the I/O using dual VIO Servers, one with dual NIC  connectors and the other with dual HBAs.

    正确答案:C

  • 第16题:

    A customer plans to consolidate several systems onto POWER7. Their immediate requirement is to have a single Power 770, and they will buy a second Power 770 at a later stage. They want to keep their existing three POWER5 570s and three POWER6 520s which are all managed by an HMC (7310-CR3). Which of these statements is true and would minimize the cost?()

    • A、All the machines can be connected to the existing HMC, as long as it is updated to code level 7.7.1 or later
    • B、The Power 770 requires an HMC (7042-CR5 or later), so they must buy one. All of the systems can be managed by this new HMC
    • C、They should buy a new HMC for the Power 770 system, and leave the POWER5 and POWER6 based  systems connected to the existing one
    • D、The Power 770 requires an HMC, so they should connect the Power 770 to the HMC and convert the POWER5 and POWER6 based servers to IVM

    正确答案:A

  • 第17题:

    A customer has requested five rack mounted servers, and a rack. They want redundant power connections. Which of the following is required to meet these requirements?()

    • A、Redundant power supplies on the servers
    • B、Redundant PDUs in the rack
    • C、edundant power supplies in the servers and redundant PDUs in the rack
    • D、Redundant power supplies in the servers, redundant PDUs in the rack, and Active Energy Manager (AEM)

    正确答案:C

  • 第18题:

    A customer has the following equipment installed in their data center:  (1)an IBM BladeCenter H chassis (2)two power supplies  (3)six HS22V blades (4)three Nortel 1/10 GB ESMs The retail customer purchased a new HX5 with MAX5.  Which of the following must be added to install the HX5 with MAX5?()

    • A、Two additional power supplies
    • B、Fibre Channel (FC) switches and SAN storage
    • C、A Nortel 1/10 GB ESM
    • D、SSD for the HX5

    正确答案:A

  • 第19题:

    A customer’s data center has all POWER4+ systems, and they plan to add three new p5-570 systems.  They will be purchasing a new 7310-CR2 HMC to support the POWER5 systems.  What is a key requirement that they need to plan for with the new HMC?()

    • A、A desk, as it not rack mountable
    • B、Ethernet connections to the POWER5 systems
    • C、Serial connections to the POWER5 systems
    • D、USB connections for the keyboard and mouse

    正确答案:B

  • 第20题:

    A customer wants to run a Domino e-mail application,a Business Intelligence database,and a batch processing application on Linux.The workloads have different behaviors and do not have peaks at the same time. What is a benefit of running these applications on a Power Systems server instead of running on separate x86 servers?()

    • A、Each Linux application can run in a Workload Partition, reducing the management efforts.
    • B、Total cost of Linux applications on Power Systems is more cost effective than on x86 because of platform licensing.
    • C、Memory cloning can be used on the Power Systems to have a single image of the Linux kernel shared by all partitions.
    • D、Using micro-partitions on Power Systems allow the workloads to share the processing resources, increasing the overall system utilization.

    正确答案:D

  • 第21题:

    单选题
    A customer plans to consolidate several systems onto POWER7. Their immediate requirement is to have a single Power 770, and they will buy a second Power 770 at a later stage. They want to keep their existing three POWER5 570s and three POWER6 520s which are all managed by an HMC (7310-CR3). Which of these statements is true and would minimize the cost?()
    A

    All the machines can be connected to the existing HMC, as long as it is updated to code level 7.7.1 or later

    B

    The Power 770 requires an HMC (7042-CR5 or later), so they must buy one. All of the systems can be managed by this new HMC

    C

    They should buy a new HMC for the Power 770 system, and leave the POWER5 and POWER6 based  systems connected to the existing one

    D

    The Power 770 requires an HMC, so they should connect the Power 770 to the HMC and convert the POWER5 and POWER6 based servers to IVM


    正确答案: B
    解析: 暂无解析

  • 第22题:

    单选题
    A customer has 5 older POWER5 systems and they want to consolidate them onto a POWER6 system. What information is important to analyze when deciding how to design the new machine using the System Planning Tool?()
    A

     vmstat and iostat data from the older machines 

    B

     The number of CPUs that were installed in the original machines 

    C

     Data from Workload Estimator (WLE) and IBM Performance Management (PM) 

    D

     Performance data that is collected from the new system after it has been put into production


    正确答案: A
    解析: 暂无解析

  • 第23题:

    单选题
    A data center has had a power outage. Which of the following should the administrator do FIRST once the power is restored? ()
    A

     Identify which systems are the most critical and bring them up by level of importance.

    B

     Retrieve the latest backup tapes for immediate system restore using the GFS rotation.

    C

     Identify the least critical systems and then power those systems on first.

    D

     Determine the cause of the power outage and install UPS systems to prevent its reoccurrence.