Companycom is installing a p5 595 with AIX 5.3. The DLPAR option for the resources cannot be selected on the HMC menus. However, the daemons are running on both the HMC and LPARs. Which of the following is a prerequisite for DLPAR functionality?()A、The r

题目

Companycom is installing a p5 595 with AIX 5.3. The DLPAR option for the resources cannot be selected on the HMC menus. However, the daemons are running on both the HMC and LPARs. Which of the following is a prerequisite for DLPAR functionality?()

  • A、The resources must be unallocated in an LPAR
  • B、The microcode on the pSeries must be current
  • C、All network adapters on the LPAR must be defined
  • D、Network connectivity and name resolution capability between HMC and LPARs

相似考题
更多“Companycom is install”相关问题
  • 第1题:

    Companycom has just purchased a p5 570 with AIX 5.3. The customer would like to add a training LPAR to the system, but no processors are available. All of the partitions are using dedicated resources. The test LPAR is using one processor and has a 90% CPU idle rate. What can be done to setup this training LPAR quickly without disabling their current environment?()

    • A、Use AIX 5.3 which supports micro-partitioning for both the test and training LPARS
    • B、Use DLPAR to move resources from the test LPAR to training when training is active
    • C、Install Partition Load Manager to share resources between the test and training environments
    • D、Install Advanced Power Virtualization and then use micro-partitioning for both the test and  training LPARs

    正确答案:D

  • 第2题:

    下面关于INSTALL IDB操作,正确的是()。

    • A、INSTALL IDB、置DXU为REMOTE、置TRU为REMOTE
    • B、INSTALL IDB、置TRU为REMOTE、置DXU为REMOTE
    • C、INSTALL IDB、TRURESET、DXURESET
    • D、INSTALL IDB、置DXU为LOCAL、置TRU为LOCAL

    正确答案:B

  • 第3题:

    A PC cannot connect to the network. A network card was purchased without documentation ordriver discs. Which of the following is the BEST way to install it into this machine?()

    • A、Download and install the drivers
    • B、Run Windows update to install drivers
    • C、Copy drivers to flash drive and install
    • D、Purchase the disc online and install

    正确答案:C

  • 第4题:

    A System x client is interested in IBM ToolsCenter Bootable Media Creator but is concerned about functions Which describes the functions of ToolsCenter Bootable Media of the following?()

    • A、Updatefirmware, update drivers, run diagnostics, install Windows
    • B、Update firmware, run diagnostics, install Windows
    • C、Update firmware, run diagnostics, install Windows, and install Linux
    • D、Update firmware, update drivers, install Windows, and install Linux

    正确答案:B

  • 第5题:

    Companycom wants the application server LPAR to communicate with the database LPAR on a p5 590 without using network adapters. What does the customer need to install?()

    • A、VIO Server
    • B、AIX 5.2 ML4
    • C、Shared Ethernet Adapter
    • D、AIX 5.3 with Advanced Power Virtualization

    正确答案:D

  • 第6题:

    Companycom has plans to deploy a large database solution. Their primary requirement is minimal user access downtime. They are comparing a single server implementation with a two server deployment. What solution would they use to avoid downtime for OS software maintenance?()

    • A、Apply OS updates once a year
    • B、Utilize a GPFS cluster solution
    • C、Implement a two server deployment with HACMP
    • D、Install a single server implementation with HACMP failover to a second LPAR

    正确答案:C

  • 第7题:

    What are the steps required to perform a Preservation install on a server?()

    • A、Shutdown the server and boot it into SMS.Select SMS menu option OS Upgrade,Preservation install for the install type,and allow upgrade to run
    • B、Shut down the server and perform a network boot from a local NIM server.Select Presevation install for the install type,and allow upgrade to run
    • C、Shutdown the server and boot it into SMS.Select SMS menu option OS Upgrade,Presevation install for the install type,and allow for upgrade to run
    • D、Re-boot the server and NFS mount the bos images from a local NIM server.Run smit install.Select Presevation install for the install type,and allow upgrade to run

    正确答案:A

  • 第8题:

    You have a server that runs Windows Server 2008 Service Pack 2 (SP2). You plan to install Exchange Server 2010 on the server. You need to install the Exchange Server 2010 prerequisites for the Mailbox, Client Access, and Hub Transport server roles.  What should you do on the server()? 

    • A、¡¤Install Microsoft .NET Framework 3.5 Service Pack 1 (SP1Install Windows Management Framework run ServerManagerCmd.exe IP Exchange-Typical.xml
    • B、¡¤Install Microsoft .NET Framework 3.5 Service Pack 1 (SP1Install Windows Remote Management (winRM) 2.0 Run ServerManagerCmd.exe IP Exchange-Base.xml
    • C、¡¤Install Windows ManagementFramework Install Message Queuing Install the Web Server role
    • D、 ¡¤Install Windows Management Framewor Install the Web Server role Install the RPC over HTTP proxy component

    正确答案:A

  • 第9题:

    A system administrator has a mksysb on tape of an AIX 5.2 machine and needs to install it on a different server. How can this be accomplished?()

    • A、Install the base AIX from 5.2 media and then install the mksysb overtop.
    • B、Mount the tape and use the tar command to install AIX and the rest of the contents of the rootvg.
    • C、Insert the mksysb tape and a 5.2 base media CD and then boot to maintenance mode and initiate the install.
    • D、Install AIX 5.2 from base media and then perform an update_all install from the mksysb tape of the original machine.

    正确答案:C

  • 第10题:

    Which of the following BEST describes the initial process of setting up a new operating system from a CD-ROM? ()

    • A、Format a partition, install device drivers, and install the operating system.
    • B、Create a partition, format the partition, and install the operating system.
    • C、Install the operating system, create a partition, and install device drivers.
    • D、Install the operating system, install device drivers, and create a partition.

    正确答案:B

  • 第11题:

    单选题
    During the Solution Assurance for a p5 590, Companycom states there is a plan to install OEM Emulex cards in the p5 590. The customer assumes there will be no problem with the plan since IBM resells the Emulex cards. What is the correct response for the customer?()
    A

    The IBM CE will install the card

    B

    The card will not be supported by IBM

    C

    The AIX device driver should work fine

    D

    The customer is correct, there should be no problem


    正确答案: D
    解析: 暂无解析

  • 第12题:

    单选题
    Which of the following BEST describes the initial process of setting up a new operating system from a CD-ROM? ()
    A

    Format a partition, install device drivers, and install the operating system.

    B

    Create a partition, format the partition, and install the operating system.

    C

    Install the operating system, create a partition, and install device drivers.

    D

    Install the operating system, install device drivers, and create a partition.


    正确答案: B
    解析: 暂无解析

  • 第13题:

    安装源代码发布软件包时,以下命令顺序正确的是:()

    • A、make;make install;make clean;./configure
    • B、./configure;make install;make clean;make
    • C、make install;make clean;make;./configure
    • D、./configure;make;make install;make clean

    正确答案:D

  • 第14题:

    在RedHat Linux 5 操作系统中,可采取哪条命令增加文件install.sh的可执行权限()

    • A、chmod +x install.sh
    • B、chmod -x install.sh   
    • C、chown +x install.sh
    • D、chown -x install.sh

    正确答案:A

  • 第15题:

    A customer has a Linux server farm and wants to use IBM Director to manage all of their systems.  Which of the following is the preferred installation of IBM Director to fully manage the Linux systems?()

    • A、Install Director Server on a Windows 2000 Server and install the Director agents on the Linux systems.
    • B、Install IBM Director Agent on a Linux server and install the Director Server on the Linux systems.
    • C、Install the Director Server on a Linux server and manage the systems via Linux native SNMP support.
    • D、Install Director Server on a Linux server and install the Director Linux agent on the Linux systems.

    正确答案:D

  • 第16题:

    Companycom is considering a large partitioned p5 590 to consolidate several smaller systems in their data center. Due to the complexity of the consolidation, the customer is asking the technical support specialist to give them a report which shows pre order PCI adapter placement and validates them against IBM's recommendations. The concern is that the factory will not install the adapters in the appropriate slots as the customer pre-selected. What IBM tool is available to provide this?()

    • A、LPAR Validation Tool (LVT)
    • B、Personal Systems Configurator (PSC)
    • C、IBM Configuration for eBusiness (eConfig)
    • D、Advanced System Management Interface (ASMI)

    正确答案:A

  • 第17题:

    What are the steps required to perform a Preservation install on a server?()

    • A、Shutdown the server and boot it into SMS.Select SMS menu option OS Upgrade, Preservation install for the install type, and allow upgrade to run.
    • B、Shut down the server and perform a network boot from a local NIM server. Select Preservation install for the install type, and allow upgrade to run.
    • C、Shutdown the server and boot it into SMS.Select SMS menu option OS Upgrade, Preservation install for the install type, and allow for upgrade to run.
    • D、Re-boot the server and NFS mount the bos images from a local NIM server. Run smit install. Select Preservation install for the install type, and allow upgrade to run.

    正确答案:A

  • 第18题:

    While planning the logical volume design of a new install, Companycom considered using a striped logical volume for performance. They want to be able to extend the logical volume in the future. Which of the following actions will provide this capability?()

    • A、Add additional logical volumes two at a time
    • B、Add additional physical volumes two at a time
    • C、Create a columned striped logical volume using -C option of mklv
    • D、Create an extendable striped logical volume using -E option of mklv

    正确答案:C

  • 第19题:

    Your company purchases 15 new 64-bit servers as follows: èFive of the servers have a single processor.    èFive of the servers have a single dual core processor. èFive of the servers have two quad core processors.   You plan to deploy Windows Server 2008 R2 on the new servers by using Windows Deployment Services (WDS).  You need to recommend a WDS install image strategy that meets the following requirements: Minimizes the number of install images   Supports the deployment of Windows Server 2008 R2 What should you recommend?()

    • A、one install image file that contains three install images
    • B、one install image file that contains a single install image
    • C、two install image files that each contain a single install image
    • D、three install image files that each contain a single install image

    正确答案:B

  • 第20题:

    You want to implement IP address to Computer Name resolving on your Windows 2000 network. How do you configure this in a NETBIOS environment?()

    • A、Install a DHCP Server
    • B、Install a DNS Server
    • C、Install a WINS Server
    • D、Install an LMHOST Converter

    正确答案:C

  • 第21题:

    During the Solution Assurance for a p5 590, Companycom states there is a plan to install OEM Emulex cards in the p5 590. The customer assumes there will be no problem with the plan since IBM resells the Emulex cards. What is the correct response for the customer?()

    • A、The IBM CE will install the card
    • B、The card will not be supported by IBM
    • C、The AIX device driver should work fine
    • D、The customer is correct, there should be no problem

    正确答案:B

  • 第22题:

    中心软件SIC存放配置文件的目录名是()

    • A、install SIC%/data
    • B、install SIC%/update
    • C、install SIC%/queue
    • D、install SIC%/conf

    正确答案:D

  • 第23题:

    单选题
    Companycom has a p5 595 with no DVD configured on this server. How can they install the Virtual IO Server code?()
    A

    From the HMC

    B

    From a NFS mount

    C

    From a FTP server

    D

    From any CD or DVD drive on another server


    正确答案: A
    解析: 暂无解析

  • 第24题:

    多选题
    下列属于盒子化安装入口脚本./install.sh参数的是()。
    A

    ./install.sh - u0

    B

    ./install.sh - u1

    C

    ./install.sh - u2

    D

    ./install.sh - u3


    正确答案: B,C
    解析: 暂无解析