Conduct a TDA
Use IBM System xConfiguratioin and Option Guide (COG)
UsexREF
Conduct aServerProven Opportunity Request for Evaluation (SPORE)
第1题:
77 Since risk is associated with most projects, the best course of action is to:
A. cover all project risks by buying appropriate insurance
B. ignore the risks, since nothing can be done about them and move forward with the project in an expeditious manner.
C. avoid projects with clear and present risks
D. eliminate all known risks prior to the execution phase of the project
E. identify various risks and implement actions to mitigate their potential impact
第2题:
59 By using Project Risk Management techniques, project managers can develop strategies that do all but which of the following:
A. Significantly reduce project risks
B. eliminate project risks
C. provide a rational basis for better decision making
D. identify risks, their impact(s), and any appropriate responses
E. None of the above
第3题:
Since risk is associated with most projects,the best course of action is to (71)
A.cover all project risks by buying appropriate insurance
B.ignore the risks,since nothing can be done about them and move forward with the project in an expeditious manner
C.avoid project with clear and present risk
D.identify various risks and implement actions to mitigate their potential impact
第4题:
Which of the following best defines the Cisco Lifecycle Services approach()
第5题:
A business partner wants to identify risks, develop action plans to manage the risks, and confirm resources required for a successful implementation of a BladeCenter solution to their customer. Which addresses this situation of the following?()
第6题:
A solution provider has proposed a pSeries solution to a new customer. The solution is complex with a number of technologies that are new to the customer. They have a tight timeline for implementation. The solution provider has not been able to get a clear understanding as to how the customer will backup the system. What would be the most appropriate action to address the risks with this solution?()
第7题:
A customer plans to deploy a disaster recovery site and requires a complete mirror of their production and test environments. They have an excellent relationship with the business partner who helped them with their initial deployment. Which of the following will help with a successful implementation?()
第8题:
The sales team has brought in the pSeries technical specialist to recommend the best solution to win the business. The customer wants the lowest purchase cost four-disk solution using an external I/O solution. Which of the following offerings provides the required base function at the lowest cost?()
第9题:
Decide not to bid.
Provide a solution in the bid.
Provide a disclaimer in the bid.
Discuss options with the customer.
第10题:
Conduct a TDA
Use IBM System xConfiguratioin and Option Guide (COG)
UsexREF
Conduct aServerProven Opportunity Request for Evaluation (SPORE)
第11题:
IBM technical support services
IBM Global Financing
IBM Global Business Services
IBM Solutions Assurance Review
第12题:
Virtualization
Replace each server with energy efficient servers
Upgrade in place to improve performance
Implement BladeCenter
第13题:
44 Which of the following risks are generally considered unpredictable:
A. business risk
B. financial risk
C. inflation
D. natural hazards
E. taxes
第14题:
Risk management allows the project manager and the project team not to(71). A.eliminate most risks during the planning phase of the project B.identify project risks C.identify impacts of various risks D.plan suitable responses
第15题:
Since risk is associated with most projects,the best course of action is to ( )
A.cover all project risks by buying appropriate insurance
B.ignore the risks,since nothing can be done about them and move forward with the project in an expeditious manner
C.avoid project with clear and present risk
D.identify various risks and implement actions to mitigate their potential impact
第16题:
A customer is involved in an IBM critical situation (CritSit). The customer recently installed iDATAPIex. The business partner has been assessed a significant penalty by IBM. Which of the following is the reason for this action by IBM?()
第17题:
A Business Partner storage specialist is proposing an IBM System Storage DS5000 solution to aninstalled EMC customer. Which IBM resource should the Business Partner engage to assist withcompetitive sales strategies against EMC?()
第18题:
A customer currently has a large group of older 1U servers. Each dedicated to aunique application. Quick provisioning of the servers is important to the customer. Which of the following approaches addresses this situation?()
第19题:
A solution provider has identified a number of risks with a configuration in a customer’s request for bid. What is the most appropriate action to take to mitigate those risks for the customer?()
第20题:
2104
ESS800
FAStT600
SSA 7133
第21题:
Competeline
Executive Briefing Center
Competitive Benchmark Center
Field Technical Support Specialist (FTSS)
第22题:
The business partner was required to perform a TDA and failed to do so
The business partner recommended a nonworking configuration
The business partner did not support the customer correctly
The business partner failed to sell Remote Technical Support (RTS)
第23题:
Sell Sysback
Conduct a SAR
Sell Supportline
Provide a project timeline
第24题:
the minimum set of services that are needed to successfully deploy and manage technology solution
system design to help ensure selection of the most appropriate products
business requirements and investments as they pertain to asset lifecycle management
technology strategies and related product lifecycles that are required to ensure minimal risks and maximum return of investment