单选题A customer is considering BladeCenter H and S chassis. Which of the following is a reason to implement BladeCenter H?()A Support for10Gb internal networkB Support for SSDC Support for integrated disk drivesD Support for8Gb FC Switch Modules

题目
单选题
A customer is considering BladeCenter H and S chassis. Which of the following is a reason to implement BladeCenter H?()
A

Support for10Gb internal network

B

Support for SSD

C

Support for integrated disk drives

D

Support for8Gb FC Switch Modules


相似考题
更多“单选题A customer is considering BladeCenter H and S chassis. Which of the following is a reason to implement BladeCenter H?()A Support for10Gb internal networkB Support for SSDC Support for integrated disk drivesD Support for8Gb FC Switch Modules”相关问题
  • 第1题:

    A customer wants to install an IBM BladeCenter infrastructure but is concerned about the cost of the full fabric internal fibre switches. Consequently, the customer is considering an N_Port ID Virtualization (NPIV) capable switch. Which of the following should be mentioned to the customer regarding the NPIV switch?()

    • A、Youcan not use an NPIV switch in the same IBM BladeCenter chassis as a Cisco Intelligent Ethernet Switch
    • B、Using blade servers with the NPIV switch will require morefibre ports on the external fibre switch
    • C、Storage devices likeFibre Channel Tape and Disk cannot be attached to the NPIV Switch but must connect to a core fabric switch.
    • D、The NPIV switch will count against the number of domains in a fabric

    正确答案:C

  • 第2题:

    A retail customer installs a BladeCenter into an existing 10/100 Ethernet network. Due to cost considerations, the customer uses Copper Pass-thru Modules. After installing this solution, the customer finds that they have no network connectivity. Which of the following at is causing the problem?()

    • A、Copper Pass-thru Modules only support 1000Mb line speeds. 
    • B、Spanning Tree has been enabled on the Copper Pass-thru Module. 
    • C、The customer does not have the latest firmware loaded on the Copper Pass-thru Module. 
    • D、The customer is using LS21 Blades 

    正确答案:A

  • 第3题:

    A customer wants to install an IBM BladeCenter infrastructure but is concerned about the cost of the full fabric internal fibre switches. Consequently, the customer is considering an N_Port ID Virtualization (NPIV) capable switch.Which of the following should be mentioned to the customer regarding the NPIV switch?()

    • A、You can not use an NPIV switch in the same IBM BladeCenter chassis as a Cisco Intelligent Ethernet Switch 
    • B、Using blade servers with the NPIV switch will require more fibre ports on the external fibre switch 
    • C、Storage devices like Fibre Channel Tape and Disk cannot be attached to the NPIV Switch but must connect to a core fabric switch
    • D、The NPIV switch will count against the number of domains in a fabric

    正确答案:C

  • 第4题:

    A customer is considering BladeCenter H and S chassis. Which of the following is a reason to implement BladeCenter H?()

    • A、Support for10Gb internal network
    • B、Support for SSD
    • C、Support for integrated disk drives
    • D、Support for8Gb FC Switch Modules

    正确答案:A

  • 第5题:

    单选题
    A customer wants to install an IBM BladeCenter infrastructure but is concerned about the cost of the full fabric internal fibre switches. Consequently, the customer is considering an N_Port ID Virtualization (NPIV) capable switch.Which of the following should be mentioned to the customer regarding the NPIV switch?()
    A

    You can not use an NPIV switch in the same IBM BladeCenter chassis as a Cisco Intelligent Ethernet Switch 

    B

    Using blade servers with the NPIV switch will require more fibre ports on the external fibre switch 

    C

    Storage devices like Fibre Channel Tape and Disk cannot be attached to the NPIV Switch but must connect to a core fabric switch

    D

    The NPIV switch will count against the number of domains in a fabric


    正确答案: C
    解析: 暂无解析

  • 第6题:

    单选题
    A banking customer plans to implement a BladeCenter H chassis. They plan for seven HS22 blades, six HX5 blades with MAX5, one 1U external Fibre Channel switch, and two 3U Fibre Channel storage devices with fourteen 146GB drives. Which is the minimum amount of rack space required to implement the solution of the following?()
    A

    32U

    B

    21U

    C

    25U

    D

    22U


    正确答案: A
    解析: 暂无解析

  • 第7题:

    单选题
    A prospect is considering a BladeCenter H chassis with the Multi-Switch Interconnect Modules. The number of Ethernet ports is important to them. What is the maximum number of Ethernet ports an HS22 blade server can support if the blade does not have any expansion blades attached?()
    A

    8 

    B

    6 

    C

    4 

    D

    2


    正确答案: C
    解析: 暂无解析

  • 第8题:

    单选题
    Which of the following services offers scheduled telephone support for complex questions on AIX systems?()
    A

    Techline

    B

    Consultline

    C

    Operational Support Services - Alert for pSeries

    D

    Operational Support Services - RS/6000 SystemWatch


    正确答案: B
    解析: 暂无解析

  • 第9题:

    单选题
    The account executive is asking about post-sales support for a new p5 HMC.  They need the pSeries technical specialist to configure an HMC with software support for the customer.  Which of the following should the specialist include in the configuration?()
    A

    Supportline

    B

    ServiceSuite

    C

    Software Maintenance Agreement (SWMA)

    D

    Machine Control Program Remote Support Agreement (MCPRSA)


    正确答案: A
    解析: 暂无解析

  • 第10题:

    单选题
    A prospect is considering a BladeCenter H chassis with the Multi-Switch Interconnect Modules. The number of Ethernet ports is important to them. What is the maximum number of Ethernet ports of an HS22 blade server can support if the blade does not have any expansion blades attached?()
    A

    8

    B

    6

    C

    4

    D

    2


    正确答案: A
    解析: 暂无解析

  • 第11题:

    单选题
    A banking customer plans to implement a BladeCenter H chassis. They plan for seven HS22 blades, six HX5 blades with MAX5, one 1U external Fibre Channel switch, and two 3U Fibre Channel storage devices with fourteen 146GB drives. Which of the following is the minimum amount of rack space required to implement the solution?()
    A

    32U 

    B

    25U 

    C

    22U 

    D

    21U


    正确答案: B
    解析: 暂无解析

  • 第12题:

    单选题
    A customer has a BladeCenter E installed and plans to migrate their current Blades to the BladeCenter H.  What options will migrate from the BladeCenter E to the BladeCenter H chassis? ()
    A

    SAN Switch modules

    B

    Blowers

    C

    Power supplies

    D

    Battery backup units


    正确答案: C
    解析: 暂无解析

  • 第13题:

    A prospect is considering a BladeCenter H chassis with the Multi-Switch Interconnect Modules. The number of Ethernet ports is important to them. What is the maximum number of Ethernet ports of an HS22 blade server can support if the blade does not have any expansion blades attached?()

    • A、8
    • B、6
    • C、4
    • D、2

    正确答案:A

  • 第14题:

    A prospect is considering a BladeCenter H chassis with the Multi-Switch Interconnect Modules. The number of Ethernet ports is important to them. What is the maximum number of Ethernet ports an HS22 blade server can support if the blade does not have any expansion blades attached?()

    • A、8 
    • B、6 
    • C、4 
    • D、2

    正确答案:A

  • 第15题:

    A medical customer wants to deploy around 8TB integrated storage on a BladeCenter.Which of the following should be discussed with this customer?()

    • A、SATA internal disks
    • B、iSCSI
    • C、Solid State Storage
    • D、SAS Internal Disk

    正确答案:A

  • 第16题:

    单选题
    A network administrator has installed an N7K-F248-25XP module into an existing chassis. The module is powered on, but the interfaces are all in VDC0. What is the reason for this?()
    A

     The chassis needs an EPLD upgrade to support the new module type.

    B

     The default VDC cannot support F2 modules.

    C

     The interfaces must be allocated into a VDC for F2 modules only.

    D

     The module has failed GOLD diagnostics, and the switch has isolated the ports to protect the integrity of the system.


    正确答案: D
    解析: 暂无解析

  • 第17题:

    单选题
    A customer wants to install an IBM BladeCenter infrastructure but is concerned about the cost of the full fabric internal fibre switches. Consequently, the customer is considering an N_Port ID Virtualization (NPIV) capable switch. Which of the following should be mentioned to the customer regarding the NPIV switch?()
    A

    Youcan not use an NPIV switch in the same IBM BladeCenter chassis as a Cisco Intelligent Ethernet Switch

    B

    Using blade servers with the NPIV switch will require morefibre ports on the external fibre switch

    C

    Storage devices likeFibre Channel Tape and Disk cannot be attached to the NPIV Switch but must connect to a core fabric switch.

    D

    The NPIV switch will count against the number of domains in a fabric


    正确答案: A
    解析: 暂无解析

  • 第18题:

    单选题
    Which implement phase service component consists of explaining the benefits and limitations of purchased support options to a customer and ensuring that the customer understands operational processes and responsibilities? Select exactly 1 answer(s) from the following:()。
    A

    Staging and System Migration

    B

    Post Implementation Support Handoff Meeting

    C

    Detailed Design Development

    D

    Staff Training


    正确答案: B
    解析: 暂无解析

  • 第19题:

    单选题
    A small business customer is interesting and requires some shared storage. They expect only 3-4 blades, but wise the storage they require 4 TB RAID 1+0. They also require Flash copy and remote mirroring. Which of the following will be an issue?()
    A

    FlashCopy is not supported on the DS3000

    B

    Remote mirroring is supported on the DS3000

    C

    FlashCopy is supported on the BladeCenter S RAIDed SAS Switch Modules

    D

    FlashCopy is not supported on BladeCenter S RAIDed SAS Switch Modules


    正确答案: A
    解析: 暂无解析

  • 第20题:

    单选题
    A medical customer wants to deploy around 8TB integrated storage on a BladeCenter.Which of the following should be discussed with this customer?()
    A

    SATA internal disks

    B

    iSCSI

    C

    Solid State Storage

    D

    SAS Internal Disk


    正确答案: B
    解析: 暂无解析

  • 第21题:

    单选题
    A customer is considering BladeCenter H and S chassis. Which of the following is a reason to implement BladeCenter H?()
    A

    Support for10Gb internal network

    B

    Support for SSD

    C

    Support for integrated disk drives

    D

    Support for8Gb FC Switch Modules


    正确答案: C
    解析: 暂无解析

  • 第22题:

    单选题
    A customer is involved in an IBM critical situation (CritSit). The customer recently installed iDATAPIex. The business partner has been assessed a significant penalty by IBM. Which of the following is the reason for this action by IBM?()
    A

    The business partner was required to perform a TDA and failed to do so

    B

    The business partner recommended a nonworking configuration

    C

    The business partner did not support the customer correctly

    D

    The business partner failed to sell Remote Technical Support (RTS)


    正确答案: C
    解析: 暂无解析

  • 第23题:

    单选题
    A retail customer installs a BladeCenter into an existing 10/100 Ethernet network. Due to cost considerations, the customer uses Copper Pass-thru Modules. After installing this solution, the customer finds that they have no network connectivity. Which of the following at is causing the problem?()
    A

    Copper Pass-thru Modules only support 1000Mb line speeds. 

    B

    Spanning Tree has been enabled on the Copper Pass-thru Module. 

    C

    The customer does not have the latest firmware loaded on the Copper Pass-thru Module. 

    D

    The customer is using LS21 Blades 


    正确答案: A
    解析: 暂无解析

  • 第24题:

    单选题
    An IT director needs to deploy 3 partitions, each using dedicated internal boot disk. Which system will support the customer requirement using the least amount of rack space?()
    A

    Power 770 servers

    B

    Power 750 servers

    C

    Power 755 servers

    D

    Power 720 servers


    正确答案: C
    解析: 暂无解析