多选题When using IBM Tivoli Monitoring Universal Agents monitors, which  three IBM Tivoli Workload Scheduler processes can be monitored by  default? ()AreptrBwriterCnetmanDmonmanEbatchmanFappservman

题目
多选题
When using IBM Tivoli Monitoring Universal Agents monitors, which  three IBM Tivoli Workload Scheduler processes can be monitored by  default? ()
A

reptr

B

writer

C

netman

D

monman

E

batchman

F

appservman


相似考题
参考答案和解析
正确答案: A,E
解析: 暂无解析
更多“多选题When using IBM Tivoli Monitoring Universal Agents monitors, which  three IBM Tivoli Workload Scheduler processes can be monitored by  default? ()AreptrBwriterCnetmanDmonmanEbatchmanFappservman”相关问题
  • 第1题:

    Which tool is available for IBM BladeCenter that allows the direct power monitoring by IBM Systems Director 6.2 through the AMM?()

    • A、PowerExecutive
    • B、Active Energy Manager (AEM)
    • C、Tivoli Provisioning Manager (TPM)
    • D、Energy Monitoring and Control (EMC)

    正确答案:B

  • 第2题:

    Which two commands are used to migrate IBM Tivoli Workload Scheduler  to version 8.5 on a UNIX system?()

    • A、 launch.sh
    • B、 wdinstspb
    • C、 SETUP.bin
    • D、 twsinst -migrate
    • E、 SETUP.bin -silent

    正确答案:C,E

  • 第3题:

    What is the location for the application server scripts? ()

    • A、 wastools directory in IBM Tivoli Workload Scheduler bin directory
    • B、 wastools directory in IBM Tivoli Workload Automation home directory
    • C、 appserver directory in IBM Tivoli Workload Scheduler parent  directory
    • D、 appserver directory in IBM Tivoli Workload Automation home directory

    正确答案:B

  • 第4题:

    A customer has the need for performance monitoring of an IBM System Storage DS8000.  Which product does the customer need()

    • A、System Storage Productivity Center
    • B、Tivoli Storage Productivity Center for Data
    • C、Tivoli Storage Productivity Center for Disk
    • D、Tivoli Storage Productivity Center for Fabric

    正确答案:C

  • 第5题:

    What is the default trace file (for Linux) that is used for the initial debugging of IBM Tivoli Federated Identity Manager Runtime?()

    • A、/opt/IBM/FIM/logs/< ITFIM Domain Name>/tivoli-common/FBT/logs/msg.log
    • B、/opt/IBM/FIM/logs/< ITFIM Domain Name>/tivoli-common/FBT/logs/trace.log
    • C、/opt/IBM/WebSphere/AppServer/profiles/<servername>/logs/<profile>/trace.log
    • D、/opt/IBM/WebSphere/AppServer/profiles/<servername>/logs/<profile>/SystemOut.log

    正确答案:B

  • 第6题:

    Which command is issued on an IBM Tivoli Workload Scheduler master  to determine link status and collect into a user created report? ()

    • A、 netstat -rn > 
    • B、 conman "sc" > 
    • C、 conman "show links" > 
    • D、 conman "disp lnk status" > 

    正确答案:B

  • 第7题:

    When using IBM Tivoli Monitoring Universal Agents monitors, which  three IBM Tivoli Workload Scheduler processes can be monitored by  default? ()

    • A、 reptr
    • B、 writer
    • C、 netman
    • D、 monman
    • E、 batchman
    • F、 appservman

    正确答案:C,D,E

  • 第8题:

    单选题
    What is the default trace file (for Linux) that is used for the initial debugging of IBM Tivoli Federated Identity Manager Runtime?()
    A

    /opt/IBM/FIM/logs/< ITFIM Domain Name>/tivoli-common/FBT/logs/msg.log

    B

    /opt/IBM/FIM/logs/< ITFIM Domain Name>/tivoli-common/FBT/logs/trace.log

    C

    /opt/IBM/WebSphere/AppServer/profiles/<servername>/logs/<profile>/trace.log

    D

    /opt/IBM/WebSphere/AppServer/profiles/<servername>/logs/<profile>/SystemOut.log


    正确答案: B
    解析: 暂无解析

  • 第9题:

    多选题
    When using IBM Tivoli Monitoring Universal Agents monitors, which  three IBM Tivoli Workload Scheduler processes can be monitored by  default? ()
    A

    reptr

    B

    writer

    C

    netman

    D

    monman

    E

    batchman

    F

    appservman


    正确答案: E,B
    解析: 暂无解析

  • 第10题:

    单选题
    Which Tivoli application has a predefined X-Agent available? ()
    A

     IBM Tivoli Storage Manager

    B

     IBM Tivoli Enterprise Console

    C

     IBM Tivoli Configuration Manager

    D

     IBM Tivoli System Automation Manager


    正确答案: D
    解析: 暂无解析

  • 第11题:

    单选题
    Which command is issued on an IBM Tivoli Workload Scheduler master  to determine link status and collect into a user created report? ()
    A

     netstat -rn > 

    B

     conman sc > 

    C

     conman show links > 

    D

     conman disp lnk status > 


    正确答案: A
    解析: 暂无解析

  • 第12题:

    单选题
    Which IBM Tivoli Workload Scheduler report will provide the job  history?()
    A

     rep2

    B

     rep3

    C

     rep7

    D

     rep8


    正确答案: B
    解析: 暂无解析

  • 第13题:

    What are two circumstances for which it may be advisable to use the  silent uninstallation method instead of an interactive method?()

    • A、 The Administrator is unable to successfully export DISPLAY to a  remote server.
    • B、 IBM Tivoli Workload Scheduler is installed on a server for which  there is no console access.
    • C、 DNS is not working properly and the server cannot be accessed  remotely to run the uninstallation script.
    • D、 TCP on the server on which IBM Tivoli Workload Scheduler is  installed is configured for half-duplex rather than full-duplex.
    • E、 The remote IBM Tivoli Workload Scheduler server is multi-homed, thus  the return connection to IBM Tivoli Workload Scheduler cannot be  established thereby requiring the use of the silent  uninstaller.

    正确答案:A,B

  • 第14题:

    Which IBM Tivoli Workload Scheduler report will provide the job  history?()

    • A、 rep2
    • B、 rep3
    • C、 rep7
    • D、 rep8

    正确答案:C

  • 第15题:

    What is the required element for encryption key management on an LTO-5 drive within a tapelibrary?()

    • A、IBM LTO Encryption Manager
    • B、IBM Tape Encryption Manager
    • C、IBM Tivoli Single Sign On Manager (SSO)
    • D、IBM Tivoli Key Lifecycle Manager (TKLM)

    正确答案:D

  • 第16题:

    An international company has a heterogeneous IBM storage environment with two IBM DS8700 systems in a Metro Mirror relationship. They also have a virtualized environment with two SVC clusters in a Global Mirror relationship. The storage administrator complains about the monitoring of copy services.  Which solution should the IBM storage specialist propose for this pain point()

    • A、System Storage Productivity Center
    • B、Tivoli Storage Productivity Center for Replication
    • C、Tivoli Storage Productivity Center for Disk
    • D、DS8000 Storage Manager

    正确答案:B

  • 第17题:

    User "twsuser" is logged on to the IBM Tivoli Workload Scheduler  Master Domain Manager server using Job Scheduling Console to update  calendar. The user receives a message: MODIFY on   CALENDAR access not granted.  What is the cause of this error?()

    • A、 Batchman process is down.
    • B、 User password has expired.
    • C、 WebSphere security is damaged.
    • D、 There are insufficient permissions in Security file.

    正确答案:D

  • 第18题:

    An IBM Tivoli Workload Scheduler administrator finds that most of  the job streams are carried forward during each production day.  Which  action should the administrator take to ensure that only a  few job streams need to be carried forward? ()

    • A、 change start of day
    • B、 disable the Carry Forward option
    • C、 cancel all job streams before start of day
    • D、 Administrator does not have to take any action

    正确答案:A

  • 第19题:

    Which IBM software technology is a key component of SONAS?()

    • A、 PowerHA 
    • B、 Tivoli Storage Manager (TSM)
    • C、 Tivoli Productivity Center (TPC) 
    • D、 General Parallel File System (GPFS)

    正确答案:D

  • 第20题:

    多选题
    What are two circumstances for which it may be advisable to use the  silent uninstallation method instead of an interactive method?()
    A

    The Administrator is unable to successfully export DISPLAY to a  remote server.

    B

    IBM Tivoli Workload Scheduler is installed on a server for which  there is no console access.

    C

    DNS is not working properly and the server cannot be accessed  remotely to run the uninstallation script.

    D

    TCP on the server on which IBM Tivoli Workload Scheduler is  installed is configured for half-duplex rather than full-duplex.

    E

    The remote IBM Tivoli Workload Scheduler server is multi-homed, thus  the return connection to IBM Tivoli Workload Scheduler cannot be  established thereby requiring the use of the silent  uninstaller.


    正确答案: B,D
    解析: 暂无解析

  • 第21题:

    多选题
    Which two commands are used to migrate IBM Tivoli Workload Scheduler  to version 8.5 on a UNIX system?()
    A

    launch.sh

    B

    wdinstspb

    C

    SETUP.bin

    D

    twsinst -migrate

    E

    SETUP.bin -silent


    正确答案: B,C
    解析: 暂无解析

  • 第22题:

    单选题
    User "twsuser" is logged on to the IBM Tivoli Workload Scheduler  Master Domain Manager server using Job Scheduling Console to update  calendar. The user receives a message: MODIFY on   CALENDAR access not granted.  What is the cause of this error?()
    A

     Batchman process is down.

    B

     User password has expired.

    C

     WebSphere security is damaged.

    D

     There are insufficient permissions in Security file.


    正确答案: C
    解析: 暂无解析

  • 第23题:

    单选题
    What is the location for the application server scripts? ()
    A

     wastools directory in IBM Tivoli Workload Scheduler bin directory

    B

     wastools directory in IBM Tivoli Workload Automation home directory

    C

     appserver directory in IBM Tivoli Workload Scheduler parent  directory

    D

     appserver directory in IBM Tivoli Workload Automation home directory


    正确答案: D
    解析: 暂无解析

  • 第24题:

    多选题
    What are two valid reasons for using IBM Tivoli Access Manager for Enterprise Single Sign-On Graphical Identification and Authentication (GINA)?()
    A

    A

    B

    B

    C

    C

    D

    D

    E

    E


    正确答案: D,E
    解析: 暂无解析