第1题:
● A calendar that identifies when a project may be performed on an activity is called a:
A Project calendar.
B Resource calendar.
C Milestone point.
D Key point.
E Work unit.
第2题:
●(74) describes, in detail, the project' s deliverables and the work required to create those deliverables.
(74) A. Product scope description
B. Project objectives
C. Product specification
D. The project scope statement
第3题:
______describes,in detail,the project's deliverables and the work required to create those deliverables.
A.Product scope description
B.Project objectives
C.Stakeholder Analysis
D.The project scope statement
第4题:
Project Quality Management processes include all the activities of the (75) that determine quality policies, objectives and responsibilities so that the project will satisfy the needs for which it was undertaken.
A.performing organization
B.project management team
C.project
D.customer
第5题:
Plan Quality is the process of identifying quality requirements and standards for the project and product and documenting how the project will demonstrate compliance ______ is a method that analyze all the costs incurred over the life of the product by investment in preventing nonconformance to requirements, appraising the product or service for conformance to requirement and failing to meet requirements.
A.Cost-Benefit analysis
B.Control charts
C.Quality function deployment
D.Cost of quality analysis
第6题:
第7题:
第8题:
第9题:
Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken.
第10题:
Project Quality Management must address the management of the project and the()ofthe project. While Project Quality Management applies to all projects,regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.
第11题:
performance
process
product
object
第12题:
persistent
continuing
permanent
continuous
第13题:
● Project Quality Management must address the management of the projecand the (72) of the project. While Project Quality Management applies to alprojects, regardless of the nature of their product, product quality measureand techniques are specific to the particular type of product produced by thproject.
A.performance
B.process
C.product
D.object
第14题:
● (72)describes, in detail, the project’s deliverables and the work required to create those deliverables.
(72)
A. Product scope description
B. Project objectives
C. Stakeholder Analysis
D. The project scope statement
第15题:
Project Quality Management must address the management of the project and the ()of the project.While Project Quality Management applies to all projects, regardless of the nature of their product,product quality measures and techniques are specific to the particular type of product produced by the project.()A.performance B.process C.product D.object
项目质量管理必需专注于对项目和项目产品的管理。当所有的项目在运用项目质量管理时,无论项目产品的本质如何,都要依据项目所产生产品的类型明确产品质量的度量和技术。
第16题:
A、OK, I have divided my report into three parts, the first part is an overview of the project.
B、OK, the project is perfect.
C、No, the project isn’t so good.
第17题:
The features and functions that characterize a product,service,or result in a project are called( )
A.statement of workB.product scopeC.product qualityD.project scope
第18题:
第19题:
第20题:
()describes, in detail, the project’s deliverables and the work required to create those deliverables.
第21题:
The () describes, in detail, the project's deliverables and the work required to create those deliverables.
第22题:
What is a reason for reviewing the user requirements document with the client?()
第23题:
Product scope description
Project objectives
Stakeholder Analysis
The project scope statement