● (73) is a method used in Critical Path Methodology for constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the logical relationships that exist between
them.
(73)
A.PERT
B.AOA
C.WBS
D.PDM
第1题:
Which of the following is not a part of reports?
A: catalogue
B: title
C: conclusion
D: methodology
第2题:
第3题:
第4题:
● The project schedule is more than a document that lays out the activities over time to represent the time dimension of the project, it is a management tool to be used for decision making. As such, the schedule is used by the project management team to (73) .
(73)
A. measure, delay, record, distribute, analyze, and direct
B. plan, schedule, monitor, control, report, and forecast
C. promote, highlight, monitor, control, forecast, and report
D. emphasize, visualize, analyze, conceptualize, report, and record
第5题:
第6题:
methodology
Methodology is the principle and techniques of teaching with no necessary reference to linguistics.
略