itgle.com

● The project schedule is more than a document that lays out the activities over time to represent the time dimension of the project, it is a management tool to be used for decision making. As such, the schedule is used by the project management team to (

题目

● The project schedule is more than a document that lays out the activities over time to represent the time dimension of the project, it is a management tool to be used for decision making. As such, the schedule is used by the project management team to (73) .

(73)

A. measure, delay, record, distribute, analyze, and direct

B. plan, schedule, monitor, control, report, and forecast

C. promote, highlight, monitor, control, forecast, and report

D. emphasize, visualize, analyze, conceptualize, report, and record


相似考题
参考答案和解析
正确答案:B
更多“● The project schedule is more than a document that lays out the activities over time to r ”相关问题
  • 第1题:

    classBitStuff{BitStuffgo(){System.out.print("bits");returnthis;}}classMoreBitsextendsBitStuff{MoreBitsgo(){System.out.print("more");returnthis;}publicstaticvoidmain(String[]args){BitStuff[]bs={newBitStuff(),newMoreBits()};for(BitStuffb:bs)b.go();}}结果为:()

    A.bitsbits

    B.bitsmore

    C.moremore

    D.编译失败


    参考答案:B

  • 第2题:

    ()are?those?costs?that?cannot?be?directly?traced?to?a specific?project?and?therefore?will?be?accumulated?and allocated?equitably?over?multiple?projects?by?some?approved and?documented?accounting?procedure.

    A.Direct costs
    B.Operation costs
    C.Indirect costs
    D.Implement costs

    答案:C
    解析:
    本题翻译:
    ()是指不能直接追溯到特定项目的成本,因此将通过一些批准和记录的会计程序在多个项目上平均累计和分配。
    A.直接成本B.运营成本C.间接成本D.实施成本
    本题考查成本的分类,不能直接的就可以理解为间接,间接成本:来自一般管理费用科目或几个项目共同负担的项目成本所分摊给本项目的费用。
    而成本管理中不是涉及运营成本、实施成本。排除BD选项。所以此题选择C选项。

  • 第3题:

    ()is a document?generated by the?creating?WBS?process?that?support the WBS,which provides?more?detailed?descriptions?of the components in the?WBS.

    A.The project?charter
    B.The?project?scope statement
    C.The?WBS dictionary
    D.The?activity list

    答案:C
    解析:
    本题翻译:()是由支持WBS的创建WBS过程生成的文档,它提供了WBS中组件的更详细描述。
    A.项目章程B.项目范围说明书C.WBS词典D.活动列表
    本题考查的是范围管理中的WBS词典,正确选项为C:WBS词典。
    在制作WBS的过程中,要给WBS的每个部分赋予一个账户编码标志符,它们是成本、进度和资源使用信息汇总的层次结构。需要生成一些配套的文件,这些文件需要和WBS配套使用,称为WBS词典。所以说WBS词典是创建WBS过程生成的支持WBS的文档,它提供了WBS中组件的更详细描述。

  • 第4题:

    [A] lies [B] lays [C] settles [D] sends


    正确答案:B

    本题考查短语动词辨析。空格处填入的动词与down搭配,相当于及物动词,其主语是the snow,宾语是a treacherous carpetlie down意为“躺下”;lay down意为“放下;记下;拟定”,如:lay down the arms/the rules(放下武器/制定规则);settle down意为“安下心来,定居”;send down只能接sb.作宾语,意为“判某人入狱”,如:He was sent down for ten years for armed robbery.(他因持械抢劫被判入狱十年。)因此[B]符合文意,意为“(大雪)吹落(一块毯子)”。

  • 第5题:

    In?project?net work?diagram,the?number?of?critical?path?is()。

    A.none
    B.only?one
    C.only?two
    D.one?or?more

    答案:D
    解析:
    本题翻译:在项目网络工作图中,关键路径的数目是()。
    A.没有B.只有一个C.只有两个D.一个或更多
    本题考查的是进度管理中的关键路径,正确选项为D一个或更多。
    在一个网络图中关键路径有一条或多条,关键路径是项目中时间最长的活动顺序,决定着可能的项目最短工期。

  • 第6题:

    【单选题】某页面中有一个1行2列的表格,其中表格行<tr>的id为r1,下列()能在表格中增加一列,并且将这一列显示在最前面。

    A.document.getElementById(“r1”).Cells(1);

    B.document.getElementById(“r1”).Cells(0);

    C.document.getElementById(“r1”).insertCell(0);

    D.document.getElementById(“r1”). insertCell(1);


    一行记录了某一记录所有字段的信息;一列记录了所有记录某一字段的信息