● Which of the following is indicative of negative float?A The late start date is earlier than the early start date.B The critical path supports the imposed end date.C The early finish date is equal to the late finish date.D When leads are employed in the

题目

● Which of the following is indicative of negative float?

A The late start date is earlier than the early start date.

B The critical path supports the imposed end date.

C The early finish date is equal to the late finish date.

D When leads are employed in the schedule.

E The project is sinking.


相似考题
更多“● Which of the following is indicative of negative float?A The late start date is earlier than the early start date.B The critical path supports the imposed end date.C The early finish date is equal to the late finish date.D When leads are employed in the”相关问题
  • 第1题:

    Free float is the amount of time that an activity may be delayed with out affecting the _____.

    A.Early start of the succeeding activities.

    B.Late start of the succeeding activities.

    C.Project finish.

    D.Cost of the project.

    E.None of the above.


    正确答案:A
    A

  • 第2题:

    Using the figure in the Special window, Activity "L" has an early start time of _____ weeks and an early finish time of _____ weeks.

    A . 11, 13

    B . 12, 14

    C . 13, 15

    D . 14, 16

    E . 15, 17


    正确答案:E

  • 第3题:

    177 Which may be employed to shorten a schedule without changing the scope of the task?

    A. Fast tracking.

    B. Crashing

    C. Releasing resources earlier from tasks which were scheduled with a late start.

    D. Alter to task priorities.

    E. A or B


    正确答案:A

  • 第4题:

    117 Using the figure in the Special window, Activity "L" has an early start time of _____ weeks and an early finish time of _____ weeks.

    A. 11, 13

    B. 12, 14

    C. 13, 15

    D. 14, 16

    E. 15, 17


    正确答案:E

  • 第5题:

    ● The critical path is calculated by

    A subtracting the end date of task one from the start date of task two.

    B determining which tasks have the least amount of total slack.

    C totaling the time for all activities.

    D determining the shortest path through the network.

    E Determining which tasks have the most slack


    正确答案:B

  • 第6题:

    ● Free float is the amount of time that an activity may be delayed with out affecting the _____.

    A Early start of the succeeding activities.

    B Late start of the succeeding activities.

    C Project finish.

    D Cost of the project.

    E None of the above.


    正确答案:A

  • 第7题:

    一旦为一个完整网络计算出活动历时,顺推法(forwardpass)与逆推法(backwardpass)就会提供()

    A.活动的总时差(float)

    B.只有最早开始(early start)与最晚开始时间(late Start)

    C.关键路径(critical path)

    D.A和C


    参考答案:D

  • 第8题:

    Examine the description of the STUDENTS table:Which two aggregate functions are valid on the START_DATE column?()

    A. SUM(start_date)

    B. AVG(start_date)

    C. COUNT(start_date)

    D. AVG(start_date, end_date)

    E. MIN(start_date)

    F. MAXIMUM(start_date)


    参考答案:C, E

  • 第9题:

    一旦为一个完整网络计算出活动历时,顺推法(forwardpass)与逆推法(backwardpass)就会提供()

    • A、活动的总时差(float)
    • B、只有最早开始(early start)与最晚开始时间(late Start)
    • C、关键路径(critical path)
    • D、A和C

    正确答案:D

  • 第10题:

    如果INMS系统收到如下航行通告:(A0897/99NOTAMCA0896/99A)PAFA错误提示为()。

    • A、Q-CODE Absent.
    • B、Activity start date(field B)substituted with arrival date.
    • C、Activity start date(field B)is missing.

    正确答案:B

  • 第11题:

    单选题
    An activity has an early start date-of the lOth and a late start date of the 19th. The activity also has a duration of 4 days. There are no nonworkdays. From the information given, ()what can be concluded about the activity?
    A

    Total float for the activity is 9 days.

    B

    The early finish date ofthe activity is the end ofthe day on the 14th.

    C

    The late finish date is the 25th.

    D

    The activity can be completed in 2 days ifthe resources devoted to it are doubled.


    正确答案: D
    解析: 暂无解析

  • 第12题:

    多选题
    Examine the description of the STUDENTS table: STD_ID NUMBER(4) COURSE_ID VARCHARD2(10) START_DATE DATE END_DATE DATE Which two aggregate functions are valid on the START_DATE column?()
    A

    SUM(start_date)

    B

    AVG(start_date)

    C

    COUNT(start_date)

    D

    AVG(start_date, end_date)

    E

    MIN(start_date)

    F

    MAXIMUM(start_date)


    正确答案: B,E
    解析: 暂无解析

  • 第13题:

    The logical relationship that communicates a delay between the start/finish of one activity and the start/finish of another activity is referred to as:

    A.Slack

    B.Free float.

    C.Restricted float.

    D.Level float.

    E.Lag


    正确答案:E
    E

  • 第14题:

    22 The logical relationship that communicates a delay between the start/finish of one activity and the start/finish of another activity is referred to as:

    A. Slack

    B. Free float.

    C. Restricted float.

    D. Level float.

    E. Lag


    正确答案:E

  • 第15题:

    An activity has an early start date-of the lOth and a late start date of the 19th. The activity also has a duration of 4 days. There are no nonworkdays. From the information given, ()what can be concluded about the activity?

    A.Total float for the activity is 9 days.

    B.The early finish date ofthe activity is the end ofthe day on the 14th.

    C.The late finish date is the 25th.

    D.The activity can be completed in 2 days ifthe resources devoted to it are doubled.


    参考答案:A

  • 第16题:

    ● The most frequently used construct in Precedent Diagramming Method is:

    A Start to Start.

    B Finish to Finish.

    C Start to Finish.

    D Finish to Start.

    E Dummy activity.


    正确答案:D

  • 第17题:

    ● Which may be employed to shorten a schedule without changing the scope of the task?

    A Fast tracking.

    B Crashing

    C Releasing resources earlier from tasks which were scheduled with a late start.

    D Alter to task priorities.

    E A or B


    正确答案:A

  • 第18题:

    ● All of the following are categories of a milestone in a schedule except:

    A End date.

    B Contract dates.

    C Key events scheduled.

    D Imposed dates.

    E Task duration.


    正确答案:E

  • 第19题:

    听力原文:From an early date bankers have made a charge for the services which they provide for their customers.

    (9)

    A.From an early date the banker have charged a commission for their services.

    B.From an early date the banker has an obligation to serve the customers.

    C.From an early date the customers have charged a commission.

    D.From an early date the customer has an obligation to serve the banker.


    正确答案:A
    解析:单句意思为“银行在一开始就会向其提供服务的客户收取费用”。make a charge和charge a commission都是“收费”的意思。

  • 第20题:

    Based on which two conditions can master Preventive Maintenance (PM) schedules be created?()

    • A、 elapsed time since the target start date or completion date of previous work generated by PM  
    • B、 difference between completion date of previous work and system date is equal to Lead Time  
    • C、 elapsed time since the target start date or completion date of the latest work orders for the asset
    • D、 metered equipment usage since the target start date or completion date of previous work generated by PM
    • E、 metered equipment usage since the target start date or completion date of the latest work order for the asset

    正确答案:A,D

  • 第21题:

    Examine the description of the STUDENTS table: STD_ID NUMBER(4) COURSE_ID VARCHARD2(10) START_DATE DATE END_DATE DATE Which two aggregate functions are valid on the START_DATE column?()

    • A、SUM(start_date)
    • B、AVG(start_date)
    • C、COUNT(start_date)
    • D、AVG(start_date, end_date)
    • E、MIN(start_date)
    • F、MAXIMUM(start_date)

    正确答案:C,E

  • 第22题:

    单选题
    一旦为一个完整网络计算出活动历时,顺推法(forwardpass)与逆推法(backwardpass)就会提供()
    A

    活动的总时差(float)

    B

    只有最早开始(early start)与最晚开始时间(late Start)

    C

    关键路径(critical path)

    D

    A和C


    正确答案: C
    解析: 暂无解析

  • 第23题:

    多选题
    Based on which two conditions can master Preventive Maintenance (PM) schedules be created?()
    A

    elapsed time since the target start date or completion date of previous work generated by PM

    B

    difference between completion date of previous work and system date is equal to Lead Time

    C

    elapsed time since the target start date or completion date of the latest work orders for the asset

    D

    metered equipment usage since the target start date or completion date of previous work generated by PM

    E

    metered equipment usage since the target start date or completion date of the latest work order for the asset


    正确答案: A,D
    解析: 暂无解析