itgle.com

The scope of a project can be expected to change if:A.The project manager must provide cost estimates without having a design conceptB.Oversimplification (underestimating) of the nature of the work occursC.The project manager is assigned after the project

题目

The scope of a project can be expected to change if:

A.The project manager must provide cost estimates without having a design concept

B.Oversimplification (underestimating) of the nature of the work occurs

C.The project manager is assigned after the project is defined, and the cost and schedule are approved

D.A clear objective is not provided

E.All of the above are possible based upon the situation


相似考题
更多“The scope of a project can be expected to change if:A.The project manager must provide cos ”相关问题
  • 第1题:

    Project(71)is an uncertain event or condition that,if it occurs,has a positive or a negative effect on at least one project objective,such as time,cost,scope,or quality.

    A.risk

    B.problem

    C.result

    D.data


    正确答案:A
    风险是一个不确定因素或条件,如果它一旦发生,可能对至少一个项目目标,如项目进度、项目成本、项目范围或项目质量产生负面或正面的影响。选项A是风险,选项B是问题,选项C是结果,选项D是数据。根据项目风险定义,风险包括两方面含义:一是未实现目标;二是不确定性。因此应选择A。

  • 第2题:

    ---- Look! The man at the gate ________ be our headmaster. He is always standing there every morning.

    --- - No, it ________ be him. He is holding a meeting in the office now.

    A.must, can’t B.must, mustn’t C.can’t, can’t D.can’t, mustn’t


    正确答案:A

  • 第3题:

    Project( )is an uncertain event or condition that,if it occurs,has a positive or a negative effect on at least one project objective,such as time,cost,scope,or quality.

    A.risk
    B.problem
    C.result
    D.data

    答案:A
    解析:
    风险不是一个不确定因素或条件,如果它一旦发生,可能对至少一个项目目标,如项目进度、项目成本、项目范围或项目质量产生负面或正面的影响。选项A是风险,选项B是问题,选项C是结果,选项D是数据。根据项目风险定义,风险包括两方面含义:一是未实现目标;二是不确定性。因此应选择A。

  • 第4题:

    中国青少年发展基金会在网上的主页地址是()。

    A.http://project-hopE.cydF.gov.cn

    B.http://project-hopE.cydF.ac

    C.http://project-hopE.cydF.edu.cn

    D.http://project-hopE.cydF.com.cn


    参考答案:C

  • 第5题:

    Project()is an uncertain event or condition that,if it occurs,has a positiveor a negative effect on at least one project objective,such as time,cost,scope, or quality.

    A.risk
    B.problem
    C.result
    D.data

    答案:A
    解析:
    风险是一个不确定因素或条件,如果它一旦发生,可能对至少一个项目目标,如项目进度、项目成本、项目范围或项目质量产生负面或正面的影响。选项A 是风险,选项B 是问题,选项 C 是结果,选项 D 是数据。根据项目风险定义,风险包括两方面含义:一是未实现目标;二是不确定性。因此应选择 A

  • 第6题:

    以下选项中哪个选项是根路径的表达方法?

    A.D:/Program Files/.Net/Project1

    B./root/.Net/Project1

    C../home/.Net/Project1

    D.file://D:/Program Files/.Net/Project1


    root/.Net/Project1