Planning activities such that predetermined resource availability pools are not exceeded is called:
A.Resource leveling.
B.Manpower leveling.
C.Resource limited planning.
D.Manpower planning.
E.Manpower contingency planning.
第1题:
5 Which of the following constitute Juran's "quality trilogy":
A. planning, inspection, control.
B. planning, improvement, control.
C. planning, organization, control.
D. product, price, customer.
E. design, build, deliver.
第2题:
I’m sure all will go well as().
A. being planned
B. planned
C. having planned
D. planning
第3题:
A.AnXMLfilecontainingalldetailsofthesystem,includingIPaddressandclusterdetails
B.Abinaryfilecontainingonlyserviceprofiles,pools,andotheritemsconfiguredafterinitialconfiguration
C.Abinaryfilecontainingalldetailsofthesystem,includingIPaddressandclusterdetails
D.AnXMLfilecontainingonlyserviceprofiles,pools,andotheritemsconfiguredafterinitialconfiguration
E.AtextfilewiththeNX-OSrunningconfiguration
第4题:
195 The basic terminology for networks includes:
A. Activities, events, manpower, skill levels and slack.
B. Activities, documentation, events, manpower and skill levels.
C. Slack, activities, events, and time estimates.
D. Time estimates, slack, sponsorship involvement, and activities.
E. Time estimates, slack time, report writing, life cycle phases, and crashing times
第5题:
A.Resourceconsumergroups
B.Resourceplans
C.Resource-plangroups
D.Resource-plandirectives
E.Alloftheabove
第6题:
ERP最核心的管理思想在于其中的()。
A.“E”字,即“Enterprise”
B.“R”字,即“Resource”
C.“P”字,即“Planning”
D.“P”字,即“Place”