Project life cycles provide a better means of measurement of progress and control. The four phases of a project are conceptual development, _____, _____, and _____.
APreliminary planning, detail planning, closeout
BImplementation, reporting, termination
CDevelopment, implementation, termination
DExecution, reporting, finishing
EImplementation, termination, post-audit review
第1题:
A comprehensive definition of scope management would be:
A.Managing a project in terms of its objective through the concept, development, implementation, and termination phases of a project.
B.Approval of the scope baseline.
C.Approval of the detailed project charter.
D.Configuration control.
E.Approved detailed planning including budgets, resource allocation, linear responsibility charts and management sponsorship.
第2题:
121 Project management/project planning is most closely aligned with:
A. Long range/strategic planning (5 years or more).
B. Intermediate range planning (1 to 5 years)
C. Short range/tactical planning (1 year or less).
D. All of the above.
E. B and C
第3题:
4 Team members want to work for a project manager that can provide them with career path planning. In which organizational form. is career path planning difficult for project employees?
A. Matrix
B Pure project
C. Project coordinator
D. Project expediter
E. Classical/traditional
第4题:
86 Team members want to work for a project manager that can provide them with career path planning. In which organizational form. is career path planning difficult for project employees?
A. Matrix
B. Pure project
C. Project coordinator
D. Project expediter
E. Classical/traditional
第5题:
● A summary WBS is usually developed in the
A Conceptual phase
B implementation phase
C planning phase
D close-out phase
E All of the above phases
第6题:
● A comprehensive definition of scope management would be:
A Managing a project in terms of its objective through the concept, development, implementation, and termination phases of a project.
B Approval of the scope baseline.
C Approval of the detailed project charter.
D Configuration control.
E Approved detailed planning including budgets, resource allocation, linear responsibility charts and management sponsorship.
第7题:
● The project life-cycle can be described as(72).
(72)
A.project concept, project planning, project execution, and project close-out
B.project planning, work authorization, and project reporting
C.project planning, project control, project definition, WBS development, and project termination
D.project concept, project execution, and project reporting
第8题:
The project life-cycle can be described as(72). A.project concept,project plannin9,project execution,and project close-out B.project planning,work authorization,and project reporting C.project planning,project control,project definition,WBS development,and project termination D.project concept,project execution,and project reporting
第9题:
第10题:
第11题:
Which of these is an accurate list of Cisco Lifecycle Services phases? Select exactly 1 answer(s) from the following:()。
第12题:
initiation planning analysis design development implementation operations and maintenance
project planning, site assessment risk assessment solution selection and acquisition, testing, and operations
prepare, plan, design, implement operate, and optimize
analysis, design, deployment testing, implementation, and production
presales, project planning, development implementation, operations testing, and operations sign- off
第13题:
Team members want to work for a project manager that can provide them with career path planning. In which organizational form. is career path planning difficult for project employees?
A . Matrix
B . Pure project
C . Project coordinator
D . Project expediter
E . Classical/traditional
第14题:
167 The project life-cycle can be described as:
A. project concept, project planning, project execution, and project close-out.
B. project planning, work authorization, and project reporting.
C. project planning, project control, project definition, WBS development, and project termination. D. project concept, project execution, and project reporting.
E. All of the above
第15题:
92 Project life cycles provide a better means of measurement of progress and control. The four phases of a project are conceptual development, _____, _____, and _____.
A. Preliminary planning, detail planning, closeout
B. Implementation, reporting, termination
C. Development, implementation, termination
D. Execution, reporting, finishing
E. Implementation, termination, post-audit review
第16题:
82 Which of the following are included in the Acquisition phase(s) of the project life cycle.
A. concept and development
B. development and planning
C. execution and phase-out
D. planning and implementation
E. concept and planning
第17题:
● Project life cycles provide a better means of measurement of progress and control. The four phases of a project are conceptual development, _____, _____, and _____.
A Preliminary planning, detail planning, closeout
B Implementation, reporting, termination
C Development, implementation, termination
D Execution, reporting, finishing
E Implementation, termination, post-audit review
第18题:
Most system development methodologies also provide (71), whose purpose is to contain the various pieces of relevant information-feasibility assessments, schedules, needs analysis, and so forth-in a single place so that they can be presented to project clients and other related parties.
A.statement of work
B.project planning
C.baseline plan
D.information system planning
第19题:
The(67)defines the phases that connect the beginning of a project to its end.
A.schedule
B.project life cycle
C.temporary
D.milestone
第20题:
The (71) defines the phases that connect the beginning of a project to its end.
A.milestone
B.schedule
C.temporary
D.project life cycle
第21题:
第22题:
第23题:
The() defines the phases that connect the beginning of a project to its end.