更多“Using the situation stated in the Special window, the schedule performance index (SPI) for WBS Element P is:A . 1.1B . 0.9C . 0.956D . 1.15E . 0.869”相关问题
  • 第1题:

    Using the situation stated in the Special window, what is the total price variance for direct material?

    A . ¥140.00

    B . ¥736.00

    C . ¥0.02

    D . ¥-350.00

    E . ¥5,850.00


    正确答案:B

  • 第2题:

    Using the problem stated in the Special window, Calculate the expected value of duration (in days) using the PERT concept of the expected duration of a task

    A . 8

    B . 8.8

    C . 9.1

    D . 9.7

    E . 10.5


    正确答案:B

  • 第3题:

    Using the situation stated in the Special window, the total price variance of direct material is:

    A . ¥80,245

    B . ¥-4,236

    C . ¥-3,479

    D . ¥1

    E . ¥83,994.00


    正确答案:C

  • 第4题:

    Using the situation stated in the Special window, WBS Element Q is _____ budget by _____ percent.

    A . Over, 16.66

    B . Under, 16.66

    C . Over, 10.0

    D . Under, 10.0

    E . None of the above.


    正确答案:A

  • 第5题:

    Using the situation stated in the Special window, which WBS element has a favorable cost variance of $150?

    A . Element P

    B . Element Q

    C . Element R

    D . Element S

    E . None of the above.


    正确答案:C

  • 第6题:

    Using the situation stated in the Special window, what is the cost performance index for Case #9?

    A . 1.1

    B . 1.91

    C . 0.83

    D . 1.2

    E . None of the above


    正确答案:A

  • 第7题:

    102 Using the situation stated in the Special window, which WBS element has a favorable cost variance of $150?

    A. Element P

    B. Element Q

    C. Element R

    D. Element S

    E. None of the above


    正确答案:C

  • 第8题:

    104 Using the situation stated in the Special window, the schedule performance index (SPI) for WBS Element P is:

    A. 1.10

    B. 0.90

    C. 0.956

    D. 1.15

    E. 0.869


    正确答案:A

  • 第9题:

    109 Using the situation stated in the Special window, what is the total fixed costs for manufacturing the widgets?

    A. $3,000

    B. $27,000

    C. $27,270

    D. $1,335

    E. $1,000


    正确答案:E

  • 第10题:

    126 Using the situation stated in the Special window, what is the labor rate cost variance?

    A. $5500.00

    B. $1500.00

    C. -$100.00

    D. -$0.10

    E. $5600.00


    正确答案:D

  • 第11题:

    132 Using the situation stated in the Special window, what is the cost performance index for Case #9?

    A. 1.10

    B. 1.91

    C. 0.83

    D. 1.20

    E. None of the above


    正确答案:A

  • 第12题:

    ● Using the WBS shown in the Special window, a typical work package would be:

    A Software development

    B Systems design

    C Coding

    D A, B, and C

    E None of the above.


    正确答案:E

  • 第13题:

    Using the situation stated in the Special window, what is the total variable costs for producing one widget?

    A . ¥1,020

    B . ¥1,010

    C . ¥1,015

    D . ¥20

    E . None of the above.


    正确答案:E

  • 第14题:

    Using the situation stated in the Special window, the labor rate cost variance is:

    A . ¥66,927

    B . ¥68,329

    C . ¥386

    D . ¥-0

    E . ¥18.36


    正确答案:D

  • 第15题:

    Using the situation stated in the Special window, a comparison of the cost schedule of August as compared to July shows that the magnitude ($ value) of the variance has _____ and the percentage change has _____.

    A . Become worse, become worse

    B . Become worse, improved

    C . Improved, increased

    D . Improved, become worse

    E . None of the above are correct


    正确答案:E

  • 第16题:

    Using the situation stated in the Special window, the cost performance index (CPI) for WBS Element R is:

    A . 0.875

    B . 1.14

    C . 0.952

    D . 0.833

    E . 1.2


    正确答案:B

  • 第17题:

    Using the situation stated in the Special window, which WBS element is behind schedule but under budget?

    A . Element P

    B . Element Q

    C . Element R

    D . Element S

    E None of the above.


    正确答案:D

  • 第18题:

    101 Using the situation stated in the Special window, which WBS element is behind schedule but under budget?

    A. Element P

    B. Element Q

    C. Element R

    D. Element S

    E. None of the above


    正确答案:D

  • 第19题:

    103 Using the situation stated in the Special window, the cost performance index (CPI) for WBS Element R is:

    A. 0.875

    B. 1.14

    C. 0.952

    D. 0.833

    E. 1.20


    正确答案:B

  • 第20题:

    106 Using the situation stated in the Special window, a comparison of the cost schedule of August as compared to July shows that the magnitude ($ value) of the variance has _____ and the percentage change has _____.

    A. Become worse, become worse

    B. Become worse, improved

    C. Improved, increased

    D. Improved, become worse

    E. None of the above are correct


    正确答案:E

  • 第21题:

    124 Using the situation stated in the Special window, what is the total variable costs for producing one widget?

    A. $1,020

    B. $1,010

    C. $1,015

    D. $20.00

    E. None of the above


    正确答案:E

  • 第22题:

    130 Using the situation stated in the Special window, what is the schedule variance for Case #8? A. 1000

    B. 2000

    C. -1000

    D. -2000

    E. 0


    正确答案:C

  • 第23题:

    136 Using the situation stated in the Special window, a comparison of the cost variance of August as compared to July shows that the magnitude ($ value) of the variance has _____ and the percentage change has _____.

    A. Become worse, become worse

    B. Become worse, improved

    C. Improved, increased

    D. Improved, become worse

    E. None of the above are correct


    正确答案:B