Using the situation stated in the Special window, the schedule performance index (SPI) for WBS Element P is:
A . 1.1
B . 0.9
C . 0.956
D . 1.15
E . 0.869
第1题:
Using the situation stated in the Special window, what is the total price variance for direct material?
A . ¥140.00
B . ¥736.00
C . ¥0.02
D . ¥-350.00
E . ¥5,850.00
第2题:
Using the problem stated in the Special window, Calculate the expected value of duration (in days) using the PERT concept of the expected duration of a task
A . 8
B . 8.8
C . 9.1
D . 9.7
E . 10.5
第3题:
Using the situation stated in the Special window, the total price variance of direct material is:
A . ¥80,245
B . ¥-4,236
C . ¥-3,479
D . ¥1
E . ¥83,994.00
第4题:
Using the situation stated in the Special window, WBS Element Q is _____ budget by _____ percent.
A . Over, 16.66
B . Under, 16.66
C . Over, 10.0
D . Under, 10.0
E . None of the above.
第5题:
Using the situation stated in the Special window, which WBS element has a favorable cost variance of $150?
A . Element P
B . Element Q
C . Element R
D . Element S
E . None of the above.
第6题:
Using the situation stated in the Special window, what is the cost performance index for Case #9?
A . 1.1
B . 1.91
C . 0.83
D . 1.2
E . None of the above
第7题:
102 Using the situation stated in the Special window, which WBS element has a favorable cost variance of $150?
A. Element P
B. Element Q
C. Element R
D. Element S
E. None of the above
第8题:
104 Using the situation stated in the Special window, the schedule performance index (SPI) for WBS Element P is:
A. 1.10
B. 0.90
C. 0.956
D. 1.15
E. 0.869
第9题:
109 Using the situation stated in the Special window, what is the total fixed costs for manufacturing the widgets?
A. $3,000
B. $27,000
C. $27,270
D. $1,335
E. $1,000
第10题:
126 Using the situation stated in the Special window, what is the labor rate cost variance?
A. $5500.00
B. $1500.00
C. -$100.00
D. -$0.10
E. $5600.00
第11题:
132 Using the situation stated in the Special window, what is the cost performance index for Case #9?
A. 1.10
B. 1.91
C. 0.83
D. 1.20
E. None of the above
第12题:
● Using the WBS shown in the Special window, a typical work package would be:
A Software development
B Systems design
C Coding
D A, B, and C
E None of the above.
第13题:
Using the situation stated in the Special window, what is the total variable costs for producing one widget?
A . ¥1,020
B . ¥1,010
C . ¥1,015
D . ¥20
E . None of the above.
第14题:
Using the situation stated in the Special window, the labor rate cost variance is:
A . ¥66,927
B . ¥68,329
C . ¥386
D . ¥-0
E . ¥18.36
第15题:
Using the situation stated in the Special window, a comparison of the cost schedule of August as compared to July shows that the magnitude ($ value) of the variance has _____ and the percentage change has _____.
A . Become worse, become worse
B . Become worse, improved
C . Improved, increased
D . Improved, become worse
E . None of the above are correct
第16题:
Using the situation stated in the Special window, the cost performance index (CPI) for WBS Element R is:
A . 0.875
B . 1.14
C . 0.952
D . 0.833
E . 1.2
第17题:
Using the situation stated in the Special window, which WBS element is behind schedule but under budget?
A . Element P
B . Element Q
C . Element R
D . Element S
E None of the above.
第18题:
101 Using the situation stated in the Special window, which WBS element is behind schedule but under budget?
A. Element P
B. Element Q
C. Element R
D. Element S
E. None of the above
第19题:
103 Using the situation stated in the Special window, the cost performance index (CPI) for WBS Element R is:
A. 0.875
B. 1.14
C. 0.952
D. 0.833
E. 1.20
第20题:
106 Using the situation stated in the Special window, a comparison of the cost schedule of August as compared to July shows that the magnitude ($ value) of the variance has _____ and the percentage change has _____.
A. Become worse, become worse
B. Become worse, improved
C. Improved, increased
D. Improved, become worse
E. None of the above are correct
第21题:
124 Using the situation stated in the Special window, what is the total variable costs for producing one widget?
A. $1,020
B. $1,010
C. $1,015
D. $20.00
E. None of the above
第22题:
130 Using the situation stated in the Special window, what is the schedule variance for Case #8? A. 1000
B. 2000
C. -1000
D. -2000
E. 0
第23题:
136 Using the situation stated in the Special window, a comparison of the cost variance of August as compared to July shows that the magnitude ($ value) of the variance has _____ and the percentage change has _____.
A. Become worse, become worse
B. Become worse, improved
C. Improved, increased
D. Improved, become worse
E. None of the above are correct