更多“Typically, during which phase in a project life cycle are most of the project expenses incurred.A . Concept phaseB . Development of design phaseC . Execution phase.D . Termination phase.E . None of the above”相关问题
  • 第1题:

    During which phase of the project life cycle is the amount at stake lowest?

    A concept

    B development

    C execution

    D conclusion

    E C and D


    正确答案:A

  • 第2题:

    67 The project stakeholders should be actively involved with the _____ phase(s) of the life cycle. A. Conceptual

    B. Development.

    C. Execution

    D. Finish

    E. All of the above


    正确答案:E

  • 第3题:

    95 Which percent of the total project labor hours are typically expended by the end of the second phase of the project life cycle?

    A. 5%

    B. 10%

    C. 15%

    D. 25%

    E. 50%


    正确答案:D

  • 第4题:

    194 During which phase of the project life cycle is the amount at stake lowest?

    A. concept

    B. development

    C. execution

    D. conclusion

    E. C and D


    正确答案:A

  • 第5题:

    92 Project life cycles provide a better means of measurement of progress and control. The four phases of a project are conceptual development, _____, _____, and _____.

    A. Preliminary planning, detail planning, closeout

    B. Implementation, reporting, termination

    C. Development, implementation, termination

    D. Execution, reporting, finishing

    E. Implementation, termination, post-audit review


    正确答案:C

  • 第6题:

    88 Typically, during which phase in a project life cycle are most of the project expenses incurred. A. Concept phase

    B. Development of design phase

    C. Execution phase.

    D. Termination phase.

    E. None of the above


    正确答案:C

  • 第7题:

    67 Life Cycle Costing:

    A. is the concept of including all costs within the total life of a project.

    B. is an activity devoted to optimizing cost/performance

    C. is an activity of appraising the cost and technical performance of a completed project.

    D. is a process of predicting the life of a project.

    E. None of the above.


    正确答案:A

  • 第8题:

    ● Which percent of the total project labor hours are typically expended by the end of the second phase of the project life cycle?

    A 5%

    B 10%

    C 15%

    D 25%

    E 50%


    正确答案:D

  • 第9题:

    ● The project life-cycle can be described as(72).

    (72)

    A.project concept, project planning, project execution, and project close-out

    B.project planning, work authorization, and project reporting

    C.project planning, project control, project definition, WBS development, and project termination

    D.project concept, project execution, and project reporting


    正确答案:A

    试题(72)分析
      关于项目周期划分正确的是  (72)  。
      A.启动、计划、执行、收尾
      B.计划、授权、报告
      C.计划、控制、方案设计、WBS的发展、终止
      D.启动、执行、报告
    参考答案
      (72)A

  • 第10题:

    The project life-cycle can be described as(72). A.project concept,project plannin9,project execution,and project close-out B.project planning,work authorization,and project reporting C.project planning,project control,project definition,WBS development,and project termination D.project concept,project execution,and project reporting


    正确答案:A
    项目的生命周期可以被描述为项目启动、项目计划,项目实施和项目收尾。

  • 第11题:

    The life cycle ofa project is a description of the various phases of the project from the beginning to the end.One of the followings is not a phase of the traditional project life cycle,itis_( )

    A.devclopment
    B.concept
    C.system analysis
    D.implementation

    答案:B
    解析:
    项目的生命周期是对项目各个阶段从开始到结束的描述,下列哪项不是一个阶段的传统项目的生命周期,他的概念阶段。A开发B概念C系统分析D实施

  • 第12题:

    The life cycle of aproject is a description of the various phases of the project from thebeginning to the end. One of the followings is not a phase of the traditionalproject life cycle, It is( ).

    A.development
    B.concept
    C.system analysis
    D.implementation

    答案:B
    解析:

  • 第13题:

    Which phase of the project life cycle typically has the highest uncertainty and risk associated with it?

    A concept

    B development

    C execution

    D conclusion

    E All of the above.


    正确答案:A

  • 第14题:

    70 Which phase of the project life cycle typically has the highest uncertainty and risk associated with it? A. concept

    B. development

    C. execution

    D. conclusion

    E. All of the above


    正确答案:A

  • 第15题:

    167 The project life-cycle can be described as:

    A. project concept, project planning, project execution, and project close-out.

    B. project planning, work authorization, and project reporting.

    C. project planning, project control, project definition, WBS development, and project termination. D. project concept, project execution, and project reporting.

    E. All of the above


    正确答案:A

  • 第16题:

    6 Typically, during which phase in a project life cycle are most of the project expenses incurred. A. Concept phase

    B Development of design phase

    C. Execution phase.

    D. Termination phase.

    E. None of the above


    正确答案:C

  • 第17题:

    185 Life Cycle Costing:

    A. is the concept of including all costs within the total life of a project.

    B. is an activity devoted to optimizing cost/performance

    C. is an activity of appraising the cost and technical performance of a completed project.

    D. is a process of predicting the life of a project.

    E. None of the above


    正确答案:A

  • 第18题:

    82 Which of the following are included in the Acquisition phase(s) of the project life cycle.

    A. concept and development

    B. development and planning

    C. execution and phase-out

    D. planning and implementation

    E. concept and planning


    正确答案:C

  • 第19题:

    ● Project life cycles provide a better means of measurement of progress and control. The four phases of a project are conceptual development, _____, _____, and _____.

    A Preliminary planning, detail planning, closeout

    B Implementation, reporting, termination

    C Development, implementation, termination

    D Execution, reporting, finishing

    E Implementation, termination, post-audit review


    正确答案:C

  • 第20题:

    ● The project stakeholders should be actively involved with the _____ phase(s) of the life cycle.

    A Conceptual

    B Development.

    C Execution

    D Finish

    E All of the above.


    正确答案:E

  • 第21题:

    Which phase of the software development requires the most development time?

    A.the design phase

    B.the testing phase

    C.the maintenance phase

    D.the development phase


    正确答案:C

  • 第22题:

    The project life-cycle can be described as().

    A.project concept, project planning, project execution, and project close-out
    B.project planning, work authorization, and project reporting
    C.project planning, project control, project definition, WBS development, and project termination
    D.project concept, project execution, and project reporting

    答案:A
    解析:
    关于项目周期划分正确的是(72)。

    A. 启动、计划、执行、收尾

    B. 计划、授权、报告

    C. 计划、控制、方案设计、WBS的发展、终止

    D. 启动、执行、报告

  • 第23题:

    The life cycle of a project is a description of the various phases of the project from the beginning to the end. One of the followings is not a phase of the traditional project life cycle, It is( ).

    A.development
    B.concept
    C.system analysis
    D.implementation

    答案:B
    解析:
    翻译:项目的生命周期是对项目各个阶段从开始到结束的描述。下列哪项不是一个阶段的传统项目的生命周期,它是概念阶段。A.开发 B.概念 C.系统分析 D.实施