Typically, during which phase in a project life cycle are most of the project expenses incurred.
A . Concept phase
B . Development of design phase
C . Execution phase.
D . Termination phase.
E . None of the above
第1题:
During which phase of the project life cycle is the amount at stake lowest?
A concept
B development
C execution
D conclusion
E C and D
第2题:
67 The project stakeholders should be actively involved with the _____ phase(s) of the life cycle. A. Conceptual
B. Development.
C. Execution
D. Finish
E. All of the above
第3题:
95 Which percent of the total project labor hours are typically expended by the end of the second phase of the project life cycle?
A. 5%
B. 10%
C. 15%
D. 25%
E. 50%
第4题:
194 During which phase of the project life cycle is the amount at stake lowest?
A. concept
B. development
C. execution
D. conclusion
E. C and D
第5题:
92 Project life cycles provide a better means of measurement of progress and control. The four phases of a project are conceptual development, _____, _____, and _____.
A. Preliminary planning, detail planning, closeout
B. Implementation, reporting, termination
C. Development, implementation, termination
D. Execution, reporting, finishing
E. Implementation, termination, post-audit review
第6题:
88 Typically, during which phase in a project life cycle are most of the project expenses incurred. A. Concept phase
B. Development of design phase
C. Execution phase.
D. Termination phase.
E. None of the above
第7题:
67 Life Cycle Costing:
A. is the concept of including all costs within the total life of a project.
B. is an activity devoted to optimizing cost/performance
C. is an activity of appraising the cost and technical performance of a completed project.
D. is a process of predicting the life of a project.
E. None of the above.
第8题:
● Which percent of the total project labor hours are typically expended by the end of the second phase of the project life cycle?
A 5%
B 10%
C 15%
D 25%
E 50%
第9题:
● The project life-cycle can be described as(72).
(72)
A.project concept, project planning, project execution, and project close-out
B.project planning, work authorization, and project reporting
C.project planning, project control, project definition, WBS development, and project termination
D.project concept, project execution, and project reporting
第10题:
The project life-cycle can be described as(72). A.project concept,project plannin9,project execution,and project close-out B.project planning,work authorization,and project reporting C.project planning,project control,project definition,WBS development,and project termination D.project concept,project execution,and project reporting
第11题:
第12题:
第13题:
Which phase of the project life cycle typically has the highest uncertainty and risk associated with it?
A concept
B development
C execution
D conclusion
E All of the above.
第14题:
70 Which phase of the project life cycle typically has the highest uncertainty and risk associated with it? A. concept
B. development
C. execution
D. conclusion
E. All of the above
第15题:
167 The project life-cycle can be described as:
A. project concept, project planning, project execution, and project close-out.
B. project planning, work authorization, and project reporting.
C. project planning, project control, project definition, WBS development, and project termination. D. project concept, project execution, and project reporting.
E. All of the above
第16题:
6 Typically, during which phase in a project life cycle are most of the project expenses incurred. A. Concept phase
B Development of design phase
C. Execution phase.
D. Termination phase.
E. None of the above
第17题:
185 Life Cycle Costing:
A. is the concept of including all costs within the total life of a project.
B. is an activity devoted to optimizing cost/performance
C. is an activity of appraising the cost and technical performance of a completed project.
D. is a process of predicting the life of a project.
E. None of the above
第18题:
82 Which of the following are included in the Acquisition phase(s) of the project life cycle.
A. concept and development
B. development and planning
C. execution and phase-out
D. planning and implementation
E. concept and planning
第19题:
● Project life cycles provide a better means of measurement of progress and control. The four phases of a project are conceptual development, _____, _____, and _____.
A Preliminary planning, detail planning, closeout
B Implementation, reporting, termination
C Development, implementation, termination
D Execution, reporting, finishing
E Implementation, termination, post-audit review
第20题:
● The project stakeholders should be actively involved with the _____ phase(s) of the life cycle.
A Conceptual
B Development.
C Execution
D Finish
E All of the above.
第21题:
Which phase of the software development requires the most development time?
A.the design phase
B.the testing phase
C.the maintenance phase
D.the development phase
第22题: