itgle.com
更多“The most precise or accurate estimate for determining project costs is the _____ estimate.A . Definitive.B . AnalogyC . BudgetD . Modified standards.E . Rule of thumb.”相关问题
  • 第1题:

    Project cash reserves are often used for adjustment in escalation factors which may be beyond the control of the project manager. Other than possibly financing (interest) costs and taxes, the three most common escalation factors involve changes in:

    A . Overhead rates, labor rates and material costs.

    B . Overhead rates, schedule slippages, and rework.

    C . Rework, cost-of-living adjustments, and overtime.

    D . Material costs, shipping cost, and scope changes.

    E . Labor rates, material costs, and cost reporting.


    正确答案:A

  • 第2题:

    144 Project cash reserves are often used for adjustment in escalation factors which may be beyond the control of the project manager. Other than possibly financing (interest) costs and taxes, the three most common escalation factors involve changes in:

    A. Overhead rates, labor rates and material costs.

    B. Overhead rates, schedule slippages, and rework.

    C. Rework, cost-of-living adjustments, and overtime.

    D. Material costs, shipping cost, and scope changes.

    E. Labor rates, material costs, and cost reporting


    正确答案:A

  • 第3题:

    177 A _____ estimate prepared from layouts, sketches and flowsheets, should be accurate within (-10, +25%).

    A. Parametric

    B. Definitive.

    C. Budget

    D. Bottom up. E

    . Top down


    正确答案:C

  • 第4题:

    19 It is argumentative whether project managers actually control costs. Which of the following is the most common element over which the project manager may have some degree of control?

    A. Direct labor dollars

    B. Direct labor hours.

    C. Overhead rates.

    D. Procurement costs.

    E. None of the above


    正确答案:B

  • 第5题:

    59 A _____ estimate prepared from layouts, sketches and flowsheets, should be accurate within (-10, +25%).

    A. Parametric

    B. Definitive.

    C. Budget

    D. Bottom up.

    E. Top down


    正确答案:C

  • 第6题:

    The scope management plan is how the team will prepare the()a document that includes descriptions of create the WBS, verify completion of the project deliverables, and control requests for changes to the project scope.

    A.project charter

    B.project scope goal

    C.project budget

    D.project scope statement


    正确答案:C

  • 第7题:

    The key benefit of( )is that it provides guidance and direction on how the project costs will be managed throughout the project.

    A.plan Cost Management
    B.Control Cost
    C.Estimate Cost
    D.Determine Budget

    答案:A
    解析:

  • 第8题:

    During planning you sit down and estimate the time needed for each task and total them to come up with the project estimate.This duration is what you commit to complete the project.What is wrong with the scenario?

    A.The team did not create the estimate and estimating tales too long using that method
    B.The team did not create the estimate and a network diagram was not used
    C.The estimate is too long and should be created by management
    D.The project estimate should be the same as the customer's required completion date

    答案:B
    解析:
    解析:当你打算坐下来评估每个任务所需的时间和总共的项目评估。在你提交完成项目估算的这个期间。依据以上场景错误的选项是( )?
    团队使用这种方法并没有产生太长时间的估计和估计故事。
    团队不需要创建估算,不需要用到网络图。
    估计太长了,应该由管理人员来制定。
    项目估算应与客户要求的完工日期相同。

  • 第9题:

    During the systems planning phase. a systems analyst conducts a( )activity to study the systems request and recommend specific action. After obtaining an authonzation to proceed. the analyst interacts with( ) to gather facts about the problem of opportunity, project scope and constraints, project benefits, and estimated development time and costs. In many cases. thesystems request does not reveal the underying problem, but only a symptom. A popular technique for investigating causesand effects is called ( )The analyst has analyzed the problem or opportunity. defined the project scope and constraints, and performed ( )to evaluate project usability, costs, benefits, and time constraints. The end product of the activity is (请作答此空) .The main content must include an estimate of time .staffing requrements, costs, benefits, and expected results for the next phase of the SDLC

    A.A.report to management
    B.A.requirement definition
    C.A.project charter
    D.A.request for proposal

    答案:C
    解析:
    在系统计划阶段,系统分析师执行一项(71初步调查),研究系统需求和具体的建议活动。在获得继续进行的授权之后,分析师与(72经理和用户)进行交互,以收集关于机会、项目范围和约束、项目收益以及估计的开发时间和成本等问题的事实。大多数情况下,系统需求只是描述了症状,而未揭示潜在的问题。一种调查因果关系的流行技术叫做(73鱼刺图)。分析师分析了问题或机会,定义了项目范围和约束,并执行(74可行性分析)来评估项目可用性、成本、收益和时间约束。此活动的最终输出是(75项目章程)。主要内容必须包括系统开发生命周期下一阶段的时间、人员需求、成本、效益和对预期结果的估计。(71)A. 案例研究 B. 需求发现 C. 初步调查 D. 业务理解(72)A. 系统用户 B. 系统拥有者 C. 经理和用户 D. 业务分析师(73)A. 鱼刺图 B. PERT图 C. 甘特图 D. 用例图(74)A. 可行性分析 B. 需求分析 C. 系统建议书 D. 实情调查(75)A. 管理层报告 B. 需求定义 C. 项目章程 D. 需求建议书

  • 第10题:

    What is the MOST accurate way to determine a project’s duration before execution?()

    • A、The project manager performs all estimates
    • B、Incorporate each individual worker’s estimates
    • C、Acquire expert estimates
    • D、There is no way to determine the duration

    正确答案:B

  • 第11题:

    Why is it important to have a final meeting on a project that has been cancelled?()

    • A、Document lessons learned
    • B、Assign responsibility
    • C、Close budget
    • D、Begin new project

    正确答案:A

  • 第12题:

    单选题
    If the organizational spending plan has allocated $100,000 for a project, and the high level budget estimate for that project is $200,000; which of the following is accurate?()
    A

    The high level budget estimates are inaccurate

    B

    The organizational spending plan is inaccurate

    C

    The budget is not aligned with the spending plan of the organization

    D

    The detailed bottom up budget will need to be adjusted


    正确答案: B
    解析: 暂无解析

  • 第13题:

    Contingency planning should include all but which of the following?

    A The development of a contingency allowance determined by combining (layering) various estimate segments to form. larger estimate segments.

    B the development of schedule alternatives and work-around

    C the management of a contingency budget

    D an assessment of project shut-down liabilities.

    E A and C


    正确答案:A

  • 第14题:

    173 The most precise or accurate estimate for determining project costs is the _____ estimate. A. Definitive.

    B. Analogy

    C. Budget

    D. Modified standards.

    E. Rule of thumb


    正确答案:A

  • 第15题:

    198 The most effective means of determining the cost of a project is to price out the _____.

    A. Work breakdown structure.

    B. Linear responsibility chart.

    C. Project charter.

    D. Scope statement.

    E. Management plan


    正确答案:A

  • 第16题:

    1 Contingency planning should include all but which of the following?

    A. The development of a contingency allowance determined by combining (layering) various estimate segments to form. larger estimate segments.

    B the development of schedule alternatives and work-around

    C. the management of a contingency budget

    D. an assessment of project shut-down liabilities.

    E. A and C


    正确答案:A

  • 第17题:

    89 A Work Berakdown Structure is most useful for:

    A. Identifying individual tasks for a project.

    B. Scheduling the start of tasks.

    C. Developing a cost estimate.

    D. Determining potential delays.

    E. A and C


    正确答案:E

  • 第18题:

    The most accurate method of determining gyrocompass error while underway is by ______.

    A.Comparing the gyro azimuth of a celestial body with the computed azimuth of the body

    B.Comparing the gyro heading with the magnetic compass heading

    C.Determining from the chart the course made good between celestial fixes

    D.It cannot be determined accurately at sea due to drift of unknown currents


    正确答案:A

  • 第19题:

    The key benefit of( )is that it provides guidance and direction on how the project costs will be managed throughout the project.

    A.Plan Cost Management
    B.Control Cost
    C. Estimate Cost
    D. Determine Budget

    答案:A
    解析:
    ( )的主要好处是它可以指导和指导项目的成本如何在项目中进行管理。A.成本管理计划B.控制成本C.成本估算D.成本预算

  • 第20题:

    During the systems planning phase. a systems analyst conducts a( )activity to study the systems request and recommend specific action. After obtaining an authonzation to proceed. the analyst interacts with(请作答此空) to gather facts about the problem of opportunity, project scope and constraints, project benefits, and estimated development time and costs. In many cases. thesystems request does not reveal the underying problem, but only a symptom. A popular technique for investigating causesand effects is called ( )The analyst has analyzed the problem or opportunity. defined the project scope and constraints, and performed ( )to evaluate project usability, costs, benefits, and time constraints. The end product of the activity is ( ) .The main content must include an estimate of time .staffing requrements, costs, benefits, and expected results for the next phase of the SDLC

    A.system users
    B.system owner
    C.managers anD.users
    D.business analysts

    答案:C
    解析:
    在系统计划阶段,系统分析师执行一项(71初步调查),研究系统需求和具体的建议活动。在获得继续进行的授权之后,分析师与(72经理和用户)进行交互,以收集关于机会、项目范围和约束、项目收益以及估计的开发时间和成本等问题的事实。大多数情况下,系统需求只是描述了症状,而未揭示潜在的问题。一种调查因果关系的流行技术叫做(73鱼刺图)。分析师分析了问题或机会,定义了项目范围和约束,并执行(74可行性分析)来评估项目可用性、成本、收益和时间约束。此活动的最终输出是(75项目章程)。主要内容必须包括系统开发生命周期下一阶段的时间、人员需求、成本、效益和对预期结果的估计。(71)A. 案例研究 B. 需求发现 C. 初步调查 D. 业务理解(72)A. 系统用户 B. 系统拥有者 C. 经理和用户 D. 业务分析师(73)A. 鱼刺图 B. PERT图 C. 甘特图 D. 用例图(74)A. 可行性分析 B. 需求分析 C. 系统建议书 D. 实情调查(75)A. 管理层报告 B. 需求定义 C. 项目章程 D. 需求建议书

  • 第21题:

    ( )is a process of monitoring the status of the project to update the project costs and manage changes to the cost baseline

    A.Plan Cost Management
    B.Estimate Costs
    C.Determine Budget
    D.Control Costs

    答案:D
    解析:
    控制成本是一个监控项目状态的过程,目的是更新项目成本并且对成本基准的变化进行管理。

  • 第22题:

    If the organizational spending plan has allocated $100,000 for a project, and the high level budget estimate for that project is $200,000; which of the following is accurate?()

    • A、The high level budget estimates are inaccurate
    • B、The organizational spending plan is inaccurate
    • C、The budget is not aligned with the spending plan of the organization
    • D、The detailed bottom up budget will need to be adjusted

    正确答案:C

  • 第23题:

    单选题
    What is the MOST accurate way to determine a project’s duration before execution?()
    A

    The project manager performs all estimates

    B

    Incorporate each individual worker’s estimates

    C

    Acquire expert estimates

    D

    There is no way to determine the duration


    正确答案: C
    解析: 暂无解析