Which of the following factors has historically been the greatest contributor to project failure?A.Planning performed by a planning group.B.Poor financial estimates.C.Lack of sufficient management reserve.D.Lack of management support.E.Not using an automa

题目

Which of the following factors has historically been the greatest contributor to project failure?

A.Planning performed by a planning group.

B.Poor financial estimates.

C.Lack of sufficient management reserve.

D.Lack of management support.

E.Not using an automated tracking tool.


相似考题
更多“Which of the following factors has historically been the greatest contributor to project failure?A.Planning performed by a planning group.B.Poor financial estimates.C.Lack of sufficient management reserve.D.Lack of management support.E.Not using an automa”相关问题
  • 第1题:

    32 Financial compensation is the primary motivational tool for which of the following management theories of programs.

    A. Zero-defects program.

    B. theory X management.

    C. theory Y management.

    D. Quality control circles.

    E. A and C


    正确答案:B

  • 第2题:

    79 Which of the following planning considerations is often overlooked?

    A. Planning for project termination.

    B. Qualified project manager assignment.

    C. Insuring top management support.

    D. Clearly defined tasks.

    E. All of the above


    正确答案:A

  • 第3题:

    161 Which of the following planning considerations is often overlooked?

    A. Planning for project termination.

    B. Qualified project manager assignment.

    C. Insuring top management support.

    D. Clearly defined tasks.

    E. All of the above.


    正确答案:A

  • 第4题:

    ● Which of the following factors has historically been the greatest contributor to project failure?

    A Planning performed by a planning group.

    B Poor financial estimates.

    C Lack of sufficient management reserve.

    D Lack of management support.

    E Not using an automated tracking tool.


    正确答案:D

  • 第5题:

    ● The inputs of developing project management plan do not include (72).

    (72)

    A. project charter

    B. stakeholder management strategy

    C. project scope statement

    D. outputs from planning processes


    正确答案:B

  • 第6题:

    The( )Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project’s requirements. A.Planning B.Executing C.Monitoring and Controlling D.Close-out


    正确答案:B
    执行(Executing)过程组由为达成项目要求而在项目管理计划中定义的工作的过程组成。

  • 第7题:

    The work breakdown structure (WBS) has been widely used in management for software development project, ( ) is generally NOT validated through the WBS.

    A.Schedule and cost

    B.Organization structuring

    C.Management coordination

    D.Quality of work


    正确答案:D

  • 第8题:

    The inputs of developing project management plan do not include().

    A. project charter
    B. stakeholder management strategy
    C.project scope statement
    D.outputs from planning processes

    答案:B
    解析:
    制定项目管理计划的输入不包括(72)
    A.项目章程 B. 干系人管理策略
    C.项目范围说明书 D. 计划过程输出

  • 第9题:

    The inputs of developing project management plan do not include ().

    A.project charter
    B.stakeholder management strategy
    C.project scope statement
    D.outputs from planning processes

    答案:B
    解析:
    制定项目管理计划的输入不包括 () 。
    A.项目章程 B.干系人管理策略
    C.项目范围说明书 D.计划过程输出

  • 第10题:

    Which of the following could BEST be used to recover a failed RAID 1 disk after it has been replaced?()

    • A、 Tape restore utilities
    • B、 Imaging utilities
    • C、 Partitioning utilities
    • D、 Array management utilities

    正确答案:D

  • 第11题:

    System configurations on the HMC have been backed up correctly. After a restore, the partitions are defined with different characteristics than the running systems. What is the most probable cause of this problem?()

    • A、The LPAR Configuration backup is corrupt
    • B、The LPAR Configuration has been altered using DLPAR
    • C、The LPAR Configuration backup was performed on a different HMC
    • D、The LPAR Configuration has been altered through the Advanced System Management Interface (ASMI) on the server after the backup was performed

    正确答案:B

  • 第12题:

    单选题
    Which of the following could BEST be used to recover a failed RAID 1 disk after it has been replaced?()
    A

     Tape restore utilities

    B

     Imaging utilities

    C

     Partitioning utilities

    D

     Array management utilities


    正确答案: D
    解析: 暂无解析

  • 第13题:

    59 By using Project Risk Management techniques, project managers can develop strategies that do all but which of the following:

    A. Significantly reduce project risks

    B. eliminate project risks

    C. provide a rational basis for better decision making

    D. identify risks, their impact(s), and any appropriate responses

    E. None of the above


    正确答案:B

  • 第14题:

    86 Which of the following factors has historically been the greatest contributor to project failure? A. Planning performed by a planning group.

    B. Poor financial estimates.

    C. Lack of sufficient management reserve.

    D. Lack of management support.

    E. Not using an automated tracking tool


    正确答案:D

  • 第15题:

    ● Scope Management:

    A entails managing the project's work content.

    B is a subset of configuration management and as such is performed by CM specialists.

    C is concerned with naming all activities performed, the end products which results and the resources consumed.

    D is not a concern of the project manager.

    E None of the above.


    正确答案:C

  • 第16题:

    ● Which of the following planning considerations is often overlooked?

    A Planning for project termination.

    B Qualified project manager assignment.

    C Insuring top management support.

    D Clearly defined tasks.

    E All of the above.


    正确答案:A

  • 第17题:

    The inputs of developing project management plan do not include(72). A.project charter B.stakeholder management strategy C.project scope statement D.outputs from planning processes


    正确答案:B
    制定项目管理计划的输入不包括干系人管理策略(stakeholder management strategy)。

  • 第18题:

    ●The project budget has been finalized.Additional work has been discovered that was not planned for in the budget or project scope.(74) could provide the fund to cover the newly discovered work item.

    (74) A. Contingency reserve

    B. Project profit

    C. Management reserve

    D. Special fund


    正确答案:C

  • 第19题:

    The project budget has been finalized.Additional work has been discovered that was not planned for in the budget or project scope. (74) could provide the fund to cover the newly discovered work item.

    A.Contingency reserve
    B.Project profit
    C.Management reserve
    D.Special fund

    答案:C
    解析:
    项目的预算还未最终确定,额外的工作已经发现,没有计划的预算或并不在项目范围内。管理储备可以提供该基金支付新发现的工作项。

  • 第20题:

    The inputs of developing project management plan do not include()

    A.project charter
    B.stakeholder management strategy
    C.project scope statement
    D.outputs from planning processes

    答案:B
    解析:
    制定项目管理计划的输入不包括:A.项目章程 B.利益相关者管理策略 C.项目范围描述 D.计划过程输出

  • 第21题:

    The inputs of developing project management plan do not include()

    • A、project charter
    • B、stakeholder management strategy
    • C、project scope statement
    • D、outputs from planning processes

    正确答案:B

  • 第22题:

    Which of the following functions can be performed using the Integrated Virtualization Manager?()

    • A、Concurrent firmware updates
    • B、Management of virtual storage
    • C、Hot add/remove of I/O drawers
    • D、Management of Capacity on Demand

    正确答案:B

  • 第23题:

    单选题
    System configurations on the HMC have been backed up correctly. After a restore, the partitions are defined with different characteristics than the running systems. What is the most probable cause of this problem?()
    A

    The LPAR Configuration backup is corrupt

    B

    The LPAR Configuration has been altered using DLPAR

    C

    The LPAR Configuration backup was performed on a different HMC

    D

    The LPAR Configuration has been altered through the Advanced System Management Interface (ASMI) on the server after the backup was performed


    正确答案: C
    解析: 暂无解析