Proper implementation of project management will guarantee that:
A.Budgets will be met.
B.Schedules will be adhered to.
C.Quality/performance will be met.
D.The project will be a success.
E.None of the above.
第1题:
The purpose of project Risk Management is to:
A Identify those factors that will adversely impact project objectives.
B Assess the impact of adverse project factors.
C Assess the probability of adverse project factors.
D A and C
E All of the above.
第2题:
197 Proper implementation of project management will guarantee that:
A. Budgets will be met.
B. Schedules will be adhered to. "
C. Quality/performance will be met.
D. The project will be a success.
E. None of the above
第3题:
161 Which of the following planning considerations is often overlooked?
A. Planning for project termination.
B. Qualified project manager assignment.
C. Insuring top management support.
D. Clearly defined tasks.
E. All of the above.
第4题:
● Scope Management:
A entails managing the project's work content.
B is a subset of configuration management and as such is performed by CM specialists.
C is concerned with naming all activities performed, the end products which results and the resources consumed.
D is not a concern of the project manager.
E None of the above.
第5题:
● Which of the following planning considerations is often overlooked?
A Planning for project termination.
B Qualified project manager assignment.
C Insuring top management support.
D Clearly defined tasks.
E All of the above.
第6题:
● Proper implementation of project management will guarantee that:
A Budgets will be met.
B Schedules will be adhered to.
C Quality/performance will be met.
D The project will be a success.
E None of the above.
第7题:
The earned value technique is a commonly used method of performance measurement.It integrates project scope,schedule,and cost measures to help the project management team assess project performance.If a project’s Cost Performance Index(CPI=EV/AC)value less than 1.0,it means that( )。 A.the cost savings for work completed B.the project is ahead of its planned schedule C.the cost overrun for work completed D.1ess work was completed than was planned
第8题:
The earned value technique is a commonlyused method of performance measurement. It integrates project scope, cost, andschedule measures to help the project management team assess projectperformance.If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, itmeans that (74).
A.the project is ahead of its planned schedule
B.less work was completed than was planned
C.the cost overrun for work completed
D.the cost under-run of performance to date
第9题:
第10题:
第11题:
第12题:
第13题:
By using Project Risk Management techniques, project managers can develop strategies that do all but which of the following:
A Significantly reduce project risks
B eliminate project risks
C provide a rational basis for better decision making
D identify risks, their impact(s), and any appropriate responses
E None of the above.
第14题:
79 Proper implementation of project management will guarantee that:
A. Budgets will be met.
B. Schedules will be adhered to.
C. Quality/performance will be met.
D. The project will be a success.
E. None of the above
第15题:
67 Life Cycle Costing:
A. is the concept of including all costs within the total life of a project.
B. is an activity devoted to optimizing cost/performance
C. is an activity of appraising the cost and technical performance of a completed project.
D. is a process of predicting the life of a project.
E. None of the above.
第16题:
● The sequential steps that define the process for successfully completing a project is:
A Implementation Plan
B a life cycle
C Development Plan
D a critical path
E Management Plan
第17题:
● The project charter:
A Expresses upper management commitment to the project.
B Provides that authority by which the project will be run.
C Establishes that organizational structure with the project.
D Specifies overall objectives and timeframe. of the project.
E All of the above.
第18题:
● A comprehensive definition of scope management would be:
A Managing a project in terms of its objective through the concept, development, implementation, and termination phases of a project.
B Approval of the scope baseline.
C Approval of the detailed project charter.
D Configuration control.
E Approved detailed planning including budgets, resource allocation, linear responsibility charts and management sponsorship.
第19题:
Project Quality Management must address the management of the project and the ()of the project.While Project Quality Management applies to all projects, regardless of the nature of their product,product quality measures and techniques are specific to the particular type of product produced by the project.()A.performance B.process C.product D.object
项目质量管理必需专注于对项目和项目产品的管理。当所有的项目在运用项目质量管理时,无论项目产品的本质如何,都要依据项目所产生产品的类型明确产品质量的度量和技术。
第20题:
( )is a project management technique for measuring project performance and progress.It has the ability to combine measurements of the project management triangle: scope , time and costs.
A.Critical path method(CPM)
B.Earned value management(EVM)
C.Net present value method (NPVM)
D.Expert judgment method(EIM)
第21题:
第22题:
第23题: