During project execution, the customer authorizes and funds a scope change which requires a major change in the schedule. The baseline schedule:
A.Now becomes the new schedule, including the changes, and the original baseline is disregarded.
B.Is still the original baseline but annotated to reflect that a change has taken place.
C.Is amended to reflect the scope change, but the original baseline is still maintained for post-project review.
D.Is meaningless since every schedule update changes the baseline (i.e., a rubber baseline.)
E.Is the same since baseline schedules cannot change once the development phase is completed.
第1题:
A.ALTER TABLE CUSTOMER RENAME CUSTOMER_CHANGE
B.ALTER TABLE CUSTOMER RENAME TO CUSTOMER_CHANGE
C.RENAME TABLE CUSTOMER TO CUSTOMER_CHANGE
D.RENAME TABLE CUSTOMER CUSTOMER_CHANGE
第2题:
第3题:
哈默和钱皮认为,有三种力量,使今天的公司陷入惊恐不安的陌生境地。他们称之为3C(Customer, Competition, Change),也就是()。
A.顾客
B.竞争
C.变化
D.上帝
第4题:
第5题:
假设需要更改表名“CUSTOMER”为“CUSTOMER_CHANGE”,可以使用()语句。
A.ALTER TABLE CUSTOMER RENAME CUSTOMER_CHANGE;
B.ALTER TABLE CUSTOMER RENAME TO CUSTOMER_CHANGE;
C.RENAME TABLE CUSTOMER TO CUSTOMER_CHANGE;
D.RENAME TABLE CUSTOMER CUSTOMER_CHANGE;
第6题:
哈默和钱皮认为,有三种力量,使今天的公司陷入惊恐不安的陌生境地。他们称之为3C(customer,competition,change),也就是()。
A.顾客
B.竞争
C.变化
D.上帝