itgle.com

The schedule risk is the _____ .A the accumulated "expected' durations which maintain project completion.B Critical Path adjusted by "high-risk" activity float.C highest risk path that maintains quality.D Critical Path when calculated with "most likely" d

题目

The schedule risk is the _____ .

A the accumulated "expected' durations which maintain project completion.

B Critical Path adjusted by "high-risk" activity float.

C highest risk path that maintains quality.

D Critical Path when calculated with "most likely" duration.

E highest risk path that contributes the most risk toward the project completion.


相似考题
更多“The schedule risk is the _____ .Athe accumulated "expected' durations which maintain proje ”相关问题
  • 第1题:

    2 The Work Breakdown Structure (WBS) is the basis for communicating:

    A. Project scope, cost control, schedule, quality

    B. Project objectives, dependencies, plan, cost control

    C. Project scope, schedule, staffing, cost control

    D. Project scope, quality, schedule, dependencies

    E. Project budget, schedule, risk factors, work assignments


    正确答案:A

  • 第2题:

    ● The Work Breakdown Structure (WBS) is the basis for communicating:

    A Project scope, cost control, schedule, quality

    B Project objectives, dependencies, plan, cost control

    C Project scope, schedule, staffing, cost control

    D Project scope, quality, schedule, dependencies

    E Project budget, schedule, risk factors, work assignments.


    正确答案:A

  • 第3题:

    I work in()IT Department of()large bank.

    Athe;a

    Ba;the

    Ca;a


    A

  • 第4题:

    194 The schedule risk is the _____ .

    A. the accumulated "expected' durations which maintain project completion.

    B. Critical Path adjusted by "high-risk" activity float.

    C. highest risk path that maintains quality.

    D. Critical Path when calculated with "most likely" duration.

    E. highest risk path that contributes the most risk toward the project completion


    正确答案:B

  • 第5题:

    The car accident happened at()crossroads a few metres away from()bank.

    Athe; / 

    B/; a

    C/; the

    Dthe; the


    D