更多“During which phase of the project life cycle is the amount at stake lowest?A conceptB developmentC executionD conclusionE C and D”相关问题
  • 第1题:

    QUEST . Which percent of the total project labor hours are typically expended by the end of the second phase of the project life cycle?

    A . 5%

    B . 10%

    C . 15%

    D . 25%

    E . 50%


    正确答案:D

  • 第2题:

    The ability to reduce risk is _____ to how far you have progressed through the project life cycle.

    A inversely proportional

    B directly proportional

    C not related

    D the responsibility of the risk executive

    E is directly proportional to the amount at stake.


    正确答案:A

  • 第3题:

    The lowest dollar amount 'at stake' is associated with the following phase of the project:

    A conceptual

    B execution

    C cut-over

    D post project evaluation

    E A and D only


    正确答案:A

  • 第4题:

    67 The project stakeholders should be actively involved with the _____ phase(s) of the life cycle. A. Conceptual

    B. Development.

    C. Execution

    D. Finish

    E. All of the above


    正确答案:E

  • 第5题:

    95 Which percent of the total project labor hours are typically expended by the end of the second phase of the project life cycle?

    A. 5%

    B. 10%

    C. 15%

    D. 25%

    E. 50%


    正确答案:D

  • 第6题:

    194 During which phase of the project life cycle is the amount at stake lowest?

    A. concept

    B. development

    C. execution

    D. conclusion

    E. C and D


    正确答案:A

  • 第7题:

    88 Typically, during which phase in a project life cycle are most of the project expenses incurred. A. Concept phase

    B. Development of design phase

    C. Execution phase.

    D. Termination phase.

    E. None of the above


    正确答案:C

  • 第8题:

    82 Which of the following are included in the Acquisition phase(s) of the project life cycle.

    A. concept and development

    B. development and planning

    C. execution and phase-out

    D. planning and implementation

    E. concept and planning


    正确答案:C

  • 第9题:

    ● Which percent of the total project labor hours are typically expended by the end of the second phase of the project life cycle?

    A 5%

    B 10%

    C 15%

    D 25%

    E 50%


    正确答案:D

  • 第10题:

    The life cycle of a project is a description of the various phases of the project from the beginning to the end. One of the followings is not a phase of the traditional project life cycleIt is().

    A.development

    B.concept

    C.system analysis

    D.implementation


    正确答案:B

  • 第11题:

    The life cycle ofa project is a description of the various phases of the project from the beginning to the end.One of the followings is not a phase of the traditional project life cycle,itis_( )

    A.devclopment
    B.concept
    C.system analysis
    D.implementation

    答案:B
    解析:
    项目的生命周期是对项目各个阶段从开始到结束的描述,下列哪项不是一个阶段的传统项目的生命周期,他的概念阶段。A开发B概念C系统分析D实施

  • 第12题:

    The life cycle of aproject is a description of the various phases of the project from thebeginning to the end. One of the followings is not a phase of the traditionalproject life cycle, It is( ).

    A.development
    B.concept
    C.system analysis
    D.implementation

    答案:B
    解析:

  • 第13题:

    Typically, during which phase in a project life cycle are most of the project expenses incurred.

    A . Concept phase

    B . Development of design phase

    C . Execution phase.

    D . Termination phase.

    E . None of the above


    正确答案:C

  • 第14题:

    Which phase of the project life cycle typically has the highest uncertainty and risk associated with it?

    A concept

    B development

    C execution

    D conclusion

    E All of the above.


    正确答案:A

  • 第15题:

    101 The lowest dollar amount 'at stake' is associated with the following phase of the project: A. conceptual

    B. execution

    C. cut-over

    D. post project evaluation

    E. A and D only


    正确答案:A

  • 第16题:

    70 Which phase of the project life cycle typically has the highest uncertainty and risk associated with it? A. concept

    B. development

    C. execution

    D. conclusion

    E. All of the above


    正确答案:A

  • 第17题:

    141 Feasibility studies occur in which life cycle phase (s)?

    A. Conceptual

    B. Conceptual or Development

    C. Execution

    D. Preliminary planning

    E. any life cycle phase


    正确答案:A

  • 第18题:

    6 Typically, during which phase in a project life cycle are most of the project expenses incurred. A. Concept phase

    B Development of design phase

    C. Execution phase.

    D. Termination phase.

    E. None of the above


    正确答案:C

  • 第19题:

    10 The ability to reduce risk is _____ to how far you have progressed through the project life cycle. A. inversely proportional

    B. directly proportional

    C. not related

    D. the responsibility of the risk executive

    E. is directly proportional to the amount at stake


    正确答案:A

  • 第20题:

    ● Feasibility studies occur in which life cycle phase (s)?

    A Conceptual

    B Conceptual or Development

    C Execution

    D Preliminary planning

    E any life cycle phase


    正确答案:A

  • 第21题:

    ● The project stakeholders should be actively involved with the _____ phase(s) of the life cycle.

    A Conceptual

    B Development.

    C Execution

    D Finish

    E All of the above.


    正确答案:E

  • 第22题:

    Which of the following statements is correct?

    A.The definition phase results in the Software Requirements Specification.

    B.Testing is optional in software life cycle.

    C.CASE tools can only aid in the design phase of a software life cycle.

    D.A change during a later phase does not require the documentation of all earlier phases to be updated.


    正确答案:A

  • 第23题:

    The life cycle of a project is a description of the various phases of the project from the beginning to the end. One of the followings is not a phase of the traditional project life cycle, It is( ).

    A.development
    B.concept
    C.system analysis
    D.implementation

    答案:B
    解析:
    翻译:项目的生命周期是对项目各个阶段从开始到结束的描述。下列哪项不是一个阶段的传统项目的生命周期,它是概念阶段。A.开发 B.概念 C.系统分析 D.实施