以下哪种不是Project Menu提供的项目导出方法?()
第1题:
92 The main player in project communication is the
A. sponsor
B. project manager
C. functional manager
D. functional team
E. All of the above
第2题:
121 The quality objectives are approved in the conceptual stage of the project by the:
A. Project Engineer
B. Project Manager
C. Functional Manager
D. Quality Assurance Manager
E. Project Owner
第3题:
18 Interfacing with the customer after project go-ahead is the responsibility of:
A. Project sponsor
B. Project team
C. Project manager
D. Functional manager
E. All of the above are possible, based upon the size and complexity of the project
第4题:
● The scope baseline/project charter is prepared by the:
A Project manager
B Project manager and project office
C Project manager, project office and functional team
D Project manager, project office, functional team and project sponsor
E Project manager, project sponsor and customer/user
第5题:
● The project life-cycle can be described as(72).
(72)
A.project concept, project planning, project execution, and project close-out
B.project planning, work authorization, and project reporting
C.project planning, project control, project definition, WBS development, and project termination
D.project concept, project execution, and project reporting
第6题:
In project management,a ( ) is a list of a project’s milestones,activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource allocation,budget and duration, linked by dependencies and scheduled events.
A.schedule
B.WBS
C.SOW
D.charter
第7题:
在Project2003中,以下关于总览项目的叙述错误的是( )。
A.总览项目可以使用户对报表体情况有所了解
B.Project 2003 提供了很多任务视图、资源视图和组合图视图
C.Project2003 提供了多个可以进行简单选择、预览和打印的内置报表
D.Project 2003 提供的报表汇集了最常用的信息集
第8题:
第9题:
第10题:
在Project 2003中,以下关于总览项目的叙述错误的是()。
第11题:
You create a Visual Studio 2010 solution that includes a WCF service project and an ASP.NET project. The service includes a method named GetPeople that takes no arguments and returns an array of Person objects. The ASP.NET application uses a proxy class to access the service. You use the Add Service Reference wizard to generate the class. After you create the proxy, you move the service endpoint to a different port. You need to configure the client to use the new service address. In addition, you must change the implementation so that calls to the client proxy will return a List
第12题:
Extract
AAF
Project Manager
Batch List
第13题:
112 Of the following, who has the ultimate responsibility for meeting project quality objectives?
A. Project Engineer
B. Project Manager
C. Functional Manager
D. Quality Assurance Manager
E. Project Owner
第14题:
10 The project charter is developed by:
A. senior management
B the customer
C. the project manager
D. both A and C
E. None of the above
第15题:
● Interfacing with the customer after project go-ahead is the responsibility of:
A Project sponsor
B Project team
C Project manager
D Functional manager
E All of the above are possible, based upon the size and complexity of the project
第16题:
● The project charter is developed by:
A senior management
B the customer
C the project manager
D both A and C
E None of the above.
第17题:
The perform. Integrated Change Contorl process is the ultimate responsibility of the(①).Although changes may be initiated verbally,they should be recorded in writtern form. and entered into the (②)system.
①A.resource manager
B.division manager
C.functional manager
D.project manager
②.A.quality management
B.configuration management
C.project manager
D.scope management
参考答案:D,D
第18题:
以下关于总揽项目的叙述错误的是()。
A.Project 2003提供了多个可以进行简单选择、预览和打印的内置报表
B.Project 2003提供了很多任务视图、资源视图和组合图视图,它们可以用不同格式显示在Project中输入的项目信息
C.Project 2003提供的报表汇集了最常用的信息集,可以用来管理项目、调整资源、控制成本、分析潜在问题以及交流进度情况
D.总揽项目可以使用户对视图的整体情况有所了解
第19题:
The Perform. Integrated Change Control process is conducted from project lnception through completion and is the ultimate responsibility of the(75)
A.change control board
B. project management office
C.project manager
D.configuration management officer
第20题:
第21题:
第22题:
哪种加工类型更适合多品种生产?()
第23题:
装配线(AssEmBly)
单件小批生产(joB-shop)
批量生产(BAtCh)
连续生产(Continuous)
项目(ProjECt)