The project charter is developed by:
A.senior management
B.the customer
C.the project manager
D.both A and C
E.None of the above.
第1题:
The project scope/charter baseline includes:
A.Summary of background conditions defining the project.
B.Organization, authority and responsibility relationships.
C.Functions to be performed.
D.Resource requirement schedule including time estimates.
E.All of the above.
第2题:
Quality control is normally performed by the _____ .
A . QA personnel
B . project team
C . operating personnel
D . project management
E . None of the above.
第3题:
The purpose of project Risk Management is to:
A Identify those factors that will adversely impact project objectives.
B Assess the impact of adverse project factors.
C Assess the probability of adverse project factors.
D A and C
E All of the above.
第4题:
10 The project charter is developed by:
A. senior management
B the customer
C. the project manager
D. both A and C
E. None of the above
第5题:
139 The project charter is a document designed to tell _____ exactly what the project entails.
A. The project manager
B. The project office
C. The project team
D. The project sponsor
E. Anyone associated with the project
第6题:
● The scope baseline/project charter is prepared by the:
A Project manager
B Project manager and project office
C Project manager, project office and functional team
D Project manager, project office, functional team and project sponsor
E Project manager, project sponsor and customer/user
第7题:
● The project charter:
A Expresses upper management commitment to the project.
B Provides that authority by which the project will be run.
C Establishes that organizational structure with the project.
D Specifies overall objectives and timeframe. of the project.
E All of the above.
第8题:
● The Develop Project Management Plan Process includes the actions necessary to define, prepare, integrate, and coordinate all constituent plans into a (75)
(75)
A. Project Scope Statement
B. Project Management Plan
C. Forecasts
D. Project Charter
第9题:
The Develop Project Management Plan Process includes the actions necessary to define,prepare,integrate,and coordinate all constituent plans into a(75). A.Project Scope Statement B.Project Management Plan C.Forecasts D.Project Charter
第10题:
第11题:
第12题:
The()provides the project manager with the authority to apply organizational resources to project activities.
第13题:
The identification, definition, and selection of the project objectives as well as the best approach to achieving the project objectives are indentified in the _____ phase of the project but first documented in the project _____.
A.Conceptual, charter/baseline.
B.Conceptual, master schedule.
C.Development, charter/baseline.
D.Development, master schedule.
E.Development, masterplan.
第14题:
A project manager can exchange information with the project team using which media?
A tactile
B audio
C olfactory
D visual
E All of the above.
第15题:
35 The project charter:
A. Expresses upper management commitment to the project.
B. Provides that authority by which the project will be run.
C. Establishes that organizational structure with the project.
D. Specifies overall objectives and timeframe. of the project.
E. All of the above
第16题:
123 The scope baseline/project charter is prepared by the:
A. Project manager
B. Project manager and project office
C. Project manager, project office and functional team
D. Project manager, project office, functional team and project sponsor
E. Project manager, project sponsor and customer/user
第17题:
92 The project charter is developed by:
A. senior management
B. the customer
C. the project manager
D. both A and C
E. None of the above
第18题:
● The project charter is developed by:
A senior management
B the customer
C the project manager
D both A and C
E None of the above.
第19题:
● The project scope/charter baseline includes:
A Summary of background conditions defining the project.
B Organization, authority and responsibility relationships.
C Functions to be performed.
D Resource requirement schedule including time estimates.
E All of the above.
第20题:
The(70)provides the project manager with the authority to apply organizational resources to project activities.
A.project management plan
B.contract
C.project human resource plan
D.project charter
第21题:
The Develop Project Management Plan Process includes the actions necessary to define, prepare, integrate, and coordinate all constituent plans into a (75).
A.Project Scope Statement
B.Project Management Plan
C.Forecasts
D.Project Charter
第22题:
第23题: