A banking customer orders three IBM BladeCenter E chassis and thirty-four HS22 blades. The customer wants to fully populate the chassis with blades where possible. Which of the following is the minimum number of power cables required to provide redundancy?()
第1题:
A banking customer orders three IBM BladeCenter E chassis and thirty-four HS22 blades. Theustomer wants to fully populate the chassis with blades where possible. Which of the following is the minimum number of power cables required to provide redundancy? ()
第2题:
A customer wants to install an IBM BladeCenter infrastructure but is concerned about the cost of the full fabric internal fibre switches. Consequently, the customer is considering an N_Port ID Virtualization (NPIV) capable switch. Which of the following should be mentioned to the customer regarding the NPIV switch?()
第3题:
A customer is interested in reducing energy consumption and infrastructure consolidation for space. The customer needs a maximum of 14 servers in 7U rack. Which IBM BladeCenter Chassis should be recommended? ()
第4题:
A customer wants to install an IBM BladeCenter infrastructure but is concerned about the cost of the full fabric internal fibre switches. Consequently, the customer is considering an N_Port ID Virtualization (NPIV) capable switch.Which of the following should be mentioned to the customer regarding the NPIV switch?()
第5题:
A banking customer plans to implement a BladeCenter H chassis. They plan for seven HS22 blades, six HX5 blades with MAX5, one 1U external Fibre Channel switch, and two 3U Fibre Channel storage devices with fourteen 146GB drives. Which of the following is the minimum amount of rack space required to implement the solution?()
第6题:
A customer has the following equipment installed in their data center: (1)an IBM BladeCenter H chassis (2)two power supplies (3)six HS22V blades (4)three Nortel 1/10 GB ESMs The retail customer purchased a new HX5 with MAX5. Which of the following must be added to install the HX5 with MAX5?()
第7题:
A customer is considering BladeCenter H and S chassis. Which of the following is a reason to implement BladeCenter H?()
第8题:
A customer has a BladeCenter E installed and plans to migrate their current Blades to the BladeCenter H. What options will migrate from the BladeCenter E to the BladeCenter H chassis? ()
第9题:
An IBM BladeCenter H chassis for the JS22 Blade servers
A concurrent KVM daughter card
A pair of IBM BladeCenter Power Supplies
A second Management Module
第10题:
Back up the AMM configuration to a file
Back up the AMM configuration to the chassis
Back up the AMM using IBM Systems Director
Back up the AMM using Tivoli Storage Manager
第11题:
12
10
8
6
第12题:
SAN Switch modules
Blowers
Power supplies
Battery backup units
第13题:
A customer recently purchased an HS22 Blade to install into their existing BCH chassis. The customer installed the blade and it was not recognized. Which ofthe following is the first question for this customer?()
第14题:
What is the maximum number of 220V power supplies that can be in a UCS chassis?()
第15题:
A customer needs to add three JS22 blade servers. The customer currently has three HS21 Blade servers and one LS41 4-socket Blade Server. Based upon this information, what additional items does the customer need to purchase? ()
第16题:
A retail customer is looking at ways to reduce power requirements. They are considering deploying two hundred IBM HS22 blades running Red Hat Linux in the IBM BladeCenter E chassis. The customer has already chosen Intel L5640 CPUs to reduce power. Which on-board storage option allows the customer to reduce power consumption of each blade?()
第17题:
A banking customer has the following requirements for an IBM BladeCenter solution with high speed fibre channel: (1)four 4-socket Microsoft SQL servers with two hot swap SAS drives (2)two physical Microsoft Active Directory Servers (3)twenty-two physical Citrix servers (4)three physical Web servers (5)one physical vCenter server (6)eight vSphere hosts Which configuration minimally satisfies these requirements?()
第18题:
A customer wants to install an IBM BladeCenter infrastructure but is concerned about the cost of the internal fibre switches. Consequently. the customer wants to use the Optical Pass-Thru Module (OPM). What TRUE statement should be mentioned to the customer regarding the OPM?()
第19题:
A banking customer deployed an IBM BladeCenter chassis with one Brocade 8Gb SAN switch module. The customer requires an 8Gb uplink or higher. Which configuration will meet this request of the following?()
第20题:
A University customer has a BladeCenter H fully populated with LS21 Blades, a single AMM, and four power modules. The BladeCenter has been running flawlessly for three months. One day an administrator discovers that they cannot view video on blades 9-12 either locally or remotely even though they still appear to be running. The video works on all of the other blades. Which of the following is the cause of the video problem?()
第21题:
Three IBMBladeCenter S chassis, three Brocade Fibre modules, six Ethernet modules
Three IBMBladeCenter E chassis, three Brocade Fibre modules, six Ethernet modules
Four IBMBladeCenter H chassis, four QLogic Fibre Channel modules, eight Ethernet modules
Three IBMBladeCenter H chassis, three QLogic Fibre Channel modules, six Ethernet modules
第22题:
BladeCenter E
BladeCenter H
BladeCenter T
BladeCenter HT
第23题:
Did you add the redundant AMM?
What is the processor wattage?
Is the AMM firmware up to date?