For any given pedestal crane,when the boom is lengthened,the lifting capacity is ______.
A.unchanged
B.increased
C.eliminated
D.decreased
第1题:
With a given load on the cargo hook,tension in a single span topping lift ______.
A.increases as the boom's angle to the horizontal increases
B.is at a maximum when the boom is at a 45° angle to the horizontal
C.increases as the boom's angle to the horizontal decreases
D.decreases as the boom's angle to the horizontal decreases
第2题:
The boom indicator on a crane will indicate the ______.
A.Length of the boom
B.Angle of the boom
C.Lifting capacity of the boom
D.Direction of the boom
第3题:
What is meant by the term“luffing the boom”of a crane ________.
A.Stopping the boom
B.Topping or lowering the boom
C.Moving the boom left or right
D.All of the above
第4题:
Which of the following statement(s)is/are TRUE regarding a twin pedestal crane set ________.
A.The cranes may be operated independently
B.The cranes may be interconnected for twin operation
C.When twinned,the crane rotation on the foundation assembly is unlimited
D.All of the above
第5题:
unchanged
increased
eliminated
decreased
第6题:
angel
length
height
angle
第7题:
Lightning
High winds
Fire aboard
All of the above
第8题:
Let go of both control levers and return to neutral position
Press the emergency stop
Notify the mate on watch
All of the above
第9题:
prevent the boom from being raised too high
prevent the boom from swinging
support the boom when not in use
prevent the boom from being lowered
第10题:
winch speed
boom strength
load radius
cable strength
第11题:
increases as the boom's angle to the horizontal increases
is at a maximum when the boom is at a 45° angle to the horizontal
increases as the boom's angle to the horizontal decreases
decreases as the boom's angle to the horizontal decreases
第12题:
length of the boom
angle of the boom
lifting capacity of the boom
direction of the boom
第13题:
The boom stops on a pedestal crane prevent the boom from ______.
A.being raised too high
B.swinging at sea
C.overloading when not in use
D.being lowered too low
第14题:
What does “evel-luffing” accomplish during crane operations ________.
A.It prevents the load from swinging when the boom level is adjusted
B.Less power is needed when topping the boom with a load on the hook
C.It maintains the height of the load above the deck
D.All of the above
第15题:
When a cargo boom or crane is rated at varying capacities,there will be a table at the controls which relates safe working load to ______.
A.winch speed
B.boom strength
C.load radius
D.cable strength
第16题:
A ()is used for lifting long heavy cargo.
第17题:
being raised too high
swinging at sea
overloading when not in use
being lowered too low
第18题:
Stopping the boom
Topping or lowering the boom
Moving the boom left or right
All of the above
第19题:
time
space
length
visibility
第20题:
Do not exceed rated load capacity of crane and container spreader or slings
During any cargo handling operation,the safety of personnel is paramount
Cargo handlers must be outfitted with adequate protection from personal injury
All the above
第21题:
unchanged
increased
eliminated
decreased
第22题:
the lifting appliance can always lift the freight within its rated load
attention should be paid in order not to break the wedge when lifting cargo
sometimes the lifting work needs other assistance other than the lifting appliance
lifting work should be done with every part fit, tightness or adhesion
第23题:
It prevents the load from swinging when the boom level is adjusted
Less power is needed when topping the boom with a load on the hook
It maintains the height of the load above the deck
All of the above