Which of the following is referred to as sunk cost:
A . management reserve
B . contingency fund
C . cost budgeted for construction under water
D . expended funds over which there is no further control
E . forecasted budget over-runs
第1题:
57 Which of the following are types of status reports?
A. document, variance, trend and exception
B. cost, trend, schedule and acquisition
C. cost, schedule, technical performance
D. analysis, cost, performance and schedule
E. All of the above.
第2题:
139 Which of the following are types of status reports?
A. document, variance, trend and exception
B. cost, trend, schedule and acquisition
C. cost, schedule, technical performance
D. analysis, cost, performance and schedule
E. All of the above
第3题:
A.OE1不计算OSPF内部COST值
B.OE2不计算OSPF内部COST值
C.ON1不计算OSPF内部COST值
D.ON2计算OSPF内部COST值
第4题:
85 Project tradeoffs are usually made by comparing _____ and constraints.
A. Time, cost, and quality
B. Time, risk, and quality
C. Risk, quality, and manpower availability
D. Cost, quality, and technical performance
E. Cost, quality, and risk