During a project review meeting, you discover that your $250,000 project has a negative schedule variance of $20,000 which equates to 12% of the work scheduled to this point of time. You can therefore conclude that:A . The project will be completed late.B

题目

During a project review meeting, you discover that your $250,000 project has a negative schedule variance of $20,000 which equates to 12% of the work scheduled to this point of time. You can therefore conclude that:

A . The project will be completed late.

B . The critical path has been lengthened.

C . the costs are being overrun.

D . Overtime will be required to maintain the original critical path.

E . None of the above.


相似考题
更多“During a project review meeting, you discover that your $250,000 project has a negative sc ”相关问题
  • 第1题:

    What's ( )job? Are ( ) British?

    A. your, your

    B. you, your

    C. your, you


    正确答案:C

  • 第2题:

    中国青少年发展基金会在网上的主页地址是()。

    A.http://project-hopE.cydF.gov.cn

    B.http://project-hopE.cydF.ac

    C.http://project-hopE.cydF.edu.cn

    D.http://project-hopE.cydF.com.cn


    参考答案:C

  • 第3题:

    在对原理图进行电气规则检查前,可以()打开规则设置界面。

    A.design-Document Options

    B.Project-Project Options

    C.Tools-Schematic Preferences

    D.Project-Configuration Manager


    Project-Project Options

  • 第4题:

    ( ) – Is Miss White __________ English teacher, Maria?

    – No, she teaches __________ geography.

    A.your;my

    B.you;mine

    C.you;us

    D.your;us


    正确答案:D

  • 第5题:

    执行菜单命令(),系统开始对项目进行编译,并生成信息报告

    A.project/compile PCB project

    B.project/project option

    C.Design/netlist/protel

    D.design/make project library


    D