151 Scope reporting is the timely determination, _____, and _____ of project progress, status data, and transforming this into structured documentation (reports) necessary to judge project performance (reporting on work packages).
A. Recording, accumulation.
B. Recording, graphical display.
C. Accumulation, graphical display.
D. Graphical display, interpretation.
E. Interpretation, analysis
第1题:
Scope reporting is the timely determination, _____, and _____ of project progress, status data, and transforming this into structured documentation (reports) necessary to judge project performance (reporting on work packages).
A.Recording, accumulation.
B.Recording, graphical display.
C.Accumulation, graphical display.
D.Graphical display, interpretation.
E.Interpretation, analysis.
第2题:
120 The Work Breakdown Structure (WBS) is the basis for communicating:
A. Project scope, cost control, schedule, quality
B. Project objectives, dependencies, plan, cost control
C. Project scope, schedule, staffing, cost control
D. Project scope, quality, schedule, dependencies
E. Project budget, schedule, risk factors, work assignments
第3题:
182 The use of the project reports:
A. are not necessary on small projects
B. provides a means whereby various levels of authority can judge project performance
C. provides insight into project areas and the effectiveness of the control systems
D. All of the above
E. B and C
第4题:
92 Project life cycles provide a better means of measurement of progress and control. The four phases of a project are conceptual development, _____, _____, and _____.
A. Preliminary planning, detail planning, closeout
B. Implementation, reporting, termination
C. Development, implementation, termination
D. Execution, reporting, finishing
E. Implementation, termination, post-audit review
第5题:
● Project life cycles provide a better means of measurement of progress and control. The four phases of a project are conceptual development, _____, _____, and _____.
A Preliminary planning, detail planning, closeout
B Implementation, reporting, termination
C Development, implementation, termination
D Execution, reporting, finishing
E Implementation, termination, post-audit review
第6题:
● Scope reporting is the timely determination, _____, and _____ of project progress, status data, and transforming this into structured documentation (reports) necessary to judge project performance (reporting on work packages).
A Recording, accumulation.
B Recording, graphical display.
C Accumulation, graphical display.
D Graphical display, interpretation.
E Interpretation, analysis.
第7题:
The earned value technique is a commonly used method of performance measurement.It integrates project scope,schedule,and cost measures to help the project management team assess project performance.If a project’s Cost Performance Index(CPI=EV/AC)value less than 1.0,it means that( )。 A.the cost savings for work completed B.the project is ahead of its planned schedule C.the cost overrun for work completed D.1ess work was completed than was planned
第8题:
The earned value technique is a commonlyused method of performance measurement. It integrates project scope, cost, andschedule measures to help the project management team assess projectperformance.If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, itmeans that (74).
A.the project is ahead of its planned schedule
B.less work was completed than was planned
C.the cost overrun for work completed
D.the cost under-run of performance to date
第9题:
The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performancIf a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that __(74)__.
A.the project is ahead of its planned schedule
B.less work was completed than was planned
C.the cost overrun for work completed
D.the cost under-run of performance to date
第10题:
第11题:
第12题:
The project()is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements,thresholds, and acceptance criteria.
第13题:
● The project (73)is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements, thresholds, and acceptance criteria.
(73)
A. work performance information
B. scope statement
C. change requests
D. process analysis
第14题:
167 The project life-cycle can be described as:
A. project concept, project planning, project execution, and project close-out.
B. project planning, work authorization, and project reporting.
C. project planning, project control, project definition, WBS development, and project termination. D. project concept, project execution, and project reporting.
E. All of the above
第15题:
193 Creation of project objectives:
A. allows for data collection and analysis and progress reporting against which standards of performance can be measured.
B. is accomplished by selection of measurable variables against which performance can be judged. C. is required before funding of the project by the project sponsor.
D. all of the above.
E. A and B only
第16题:
33 Scope reporting is the timely determination, _____, and _____ of project progress, status data, and transforming this into structured documentation (reports) necessary to judge project performance (reporting on work packages).
A. Recording, accumulation.
B. Recording, graphical display.
C. Accumulation, graphical display.
D. Graphical display, interpretation.
E. Interpretation, analysis
第17题:
● The use of the project reports:
A are not necessary on small projects
B provides a means whereby various levels of authority can judge project performance
C provides insight into project areas and the effectiveness of the control systems
D All of the above
E B and C
第18题:
● The project life-cycle can be described as(72).
(72)
A.project concept, project planning, project execution, and project close-out
B.project planning, work authorization, and project reporting
C.project planning, project control, project definition, WBS development, and project termination
D.project concept, project execution, and project reporting
第19题:
A、project scope statement
B、work package
C、WBS
D、project scope plan
第20题:
●The project manager must maintain an effective communication link with the customer's satisfaction with the progress of the project. The project manager maintains this link through (71).
(71)
A.periodic project reports, periodic visits to the customer, and telephonic exchanges
B.subordinates, project team members, and the project sponsor
C.one-time reports, weekly reports, and monthly reports
D.the telephone, facsimile, and data transmission
第21题:
第22题:
第23题: