In Project Risk Management, Risk Response may include actions to:A reduce the probability of risk eventsB change the scope, budget, schedule or quality specifications of the projectC reduce the consequences or severity of impacts of a potential risk event

题目

In Project Risk Management, Risk Response may include actions to:

A reduce the probability of risk events

B change the scope, budget, schedule or quality specifications of the project

C reduce the consequences or severity of impacts of a potential risk event

D A and C

E All of the above.


相似考题
更多“In Project Risk Management, Risk Response may include actions to:Areduce the probability o ”相关问题
  • 第1题:

    _____

    [A] thought [B] sight [C] cost [D] risk


    正确答案:A

    本题测试词义搭配。空格相关意思是“一想到他即将要做的,即使他自己也….” “At thought of ”意为“一看到…”; at sight of意为年“一看见”;at cost of 意为“以…的代价”;at risk of意为“冒着….的危险”,所以选A

  • 第2题:

    Risk ( )acknowledge the existence of a threat ,but no proactive action is taken。

    A、avoidance

    B、transfer

    C、mitigate

    D、acceptance


    参考答案:D

  • 第3题:

    ( ) management includes negotiating the terms and conditions in contracts and ensuring compliance with. the terms and conditions, as well as documenting and agreeing on any changes or amendments that may arise during its implementation or execution.

    A.Contract
    B.Document
    C.Communication
    D.Risk

    答案:A
    解析:
    (合同)管理包括合同中的谈判条款和条件,并确保遵守条款和条件,以及记录和商定实施或执行过程中可能出现的任何变更或修正。

  • 第4题:

    请选择(6)处最佳答案( )。

    A.thought

    B.sight

    C.cost

    D.risk


    正确答案:A
    本题测试词义搭配。空格相关意思是“一想到他即将要做的,即使他自己也….” “At thought of ”意为“一看到…”; at sight of意为年“一看见”;at cost of 意为“以…的代价”;at risk of意为“冒着….的危险”,所以选A。

  • 第5题:

    management includes negotiating the terms and conditions in contracts and ensuring compliance with the terms and conditions,as well as documenting and agreeing on any changes or amendments that may arise during its implementation or execution

    A.Contract

    B.Document

    C.Communication

    D.Risk


    正确答案:A
    本题目翻译:干系人管理包括协商的条款和条件的合同,并确保遵守的条款和条件,以及记录和商定其实施或执行过程中可能出现的任何改变或修正。考察的是干系人管理。

  • 第6题:

    Risk()acknowledge the existence of a threat,but no proactive action is taken

    A.Avoidance
    B.Transfer
    C.Mitigate
    D.ceptance

    答案:D
    解析:
    风险()承认存在威胁,但不采取主动行动。