98 Cost management includes:
A. Cost estimating/forecasting.
B. Cost budgeting/cost control.
C. Cost applications.
D. All of the above.
E. A and B only
第1题:
Range estimating in determining cost risk probabilities requires _____ .
A an amount of financial exposure.
B risks and opportunities ranked in order of bottom line importance
C contingency requirements for expected level of confidence
D probability of cost overrun occurrences
E All of the above.
第2题:
105 Standard of purchased material:
A. Simplifies inventory control
B. reduces the risk of obsolescence
C. reduces cost of purchasing and storage
D. All of the above.
E. A and C only
第3题:
99 Scope management is:
A. a project control function.
B. employs change control.
C. a work authorization process.
D. considers Cost, Quality and Schedule.
E. All of the above
第4题:
84 In which of the following cost estimating techniques are statistics models used:
A. nonparametric cost estimating
B. parametric cost estimating
C. life cycle cost estimating
D. bottom-up estimating
E. All of the above.
第5题:
137 Range estimating in determining cost risk probabilities requires _____ .
A. an amount of financial exposure.
B. risks and opportunities ranked in order of bottom line importance
C. contingency requirements for expected level of confidence
D. probability of cost overrun occurrences
E. All of the above
第6题:
98 Which of the following statements about the cost of quality are true?
A. the cost of quality is the expense of nonconformance to requirements and specifications.
B. the cost of quality are mostly the direct responsibility of workers who are manufacturing the product.
C. quality control programs should be implemented when the cost of quality are deemed affordable by management.
D. A and B.
E. A and C
第7题:
Estimating schedule activity costs involves developing an(69)of the costs of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. For example, in most application areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. The cost estimating process considers whether the expected savings can offset the cost of the additional design work. Cost estimates are generally expressed in units of(70)to facilitate comparisons both within and across projects.The(71 )describes the business need, justification, requirements, and current boundaries for the project. It provides important information about project requirements that is considered during cost estimating.
A.accuracy
B.approximation
C.specification
D.summary
第8题:
Estimating schedule activity costs involves developing an(4)of the cost of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. For example, in mostapplication areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. The cost estimating process considers whether the expected savings can offset the cost of the additional design work. Cost estmates are generally expressed in units of(5)to facilitate comparisions both within and across projects. The(6)describes important information about project requirement that is considered during cost estimating.
A.accuracy
B.approxination
C.specification
D.summary
第9题:
第10题:
Estimating schedule activity costs involves developing an (1) of the cost of theresources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. for example, in most application areas, additionalwork during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. the cost estimating process considers whether the expected savings can offset the cost of the additional design work. cost estimates are generally expressed in units of (2) to facilitate comparisons both within and across projects.the (3) describes important information about project requirement that is considered during cost estimating. 空白(1)处填()
第11题:
In IBM Maximo Asset Management V6.2, what does the Purchase Orders applications Distribute Costs action do?()
第12题:
Distribute the line item cost among all lines.
Distribute the line item cost among all direct issue lines.
Distribute the line item cost among multiple GL accounts.
Distribute the purchase order cost among multiple GL accounts.
第13题:
87 Which of the following would most likely increase the accuracy of estimating the project cost? A. Pricing out the work at lower levels in the work breakdown structure.
B. Using historical data.
C. Talking to people who have worked on similar projects.
D. All of the above.
E. A and C only.
第14题:
155 A(n) _____ system is designed to ensure the timely availability of nonhuman resources, and includes the cost in procurement, shipping/freight, storage and loss.
A. Inventory control.
B. Materials management.
C. Procurement.
D. All of the above.
E. A and C only
第15题:
146 The planned cost for the total project at its inception is called the _____.
A. Cost of goods sold.
B. Depreciable value.
C. Budgeted cost.
D. All of the above.
E. B and C only
第16题:
127 Cost management includes processes that are required to maintain financial control of projects. These processes may include:
A. economic evaluation
B. cost estimating
C. cost forecasting
D. B and C
E. All of the above
第17题:
166 In which of the following cost estimating techniques are statistics models used:
A. nonparametric cost estimating
B. parametric cost estimating
C. life cycle cost estimating
D. bottom-up estimating
E. All of the above
第18题:
180 Cost management includes:
A. Cost estimating/forecasting.
B. Cost budgeting/cost control.
C. Cost applications.
D. All of the above.
E. A and B only
第19题:
“Cost of quality”is a project management concept that includes cost of( 73)
A.exceedings requirements
B.Changes to the requirements
C.Ensuring conformance to requirements
D.The quality control requirements
第20题:
第21题:
Which two statements about spanning tree path cost are true?()
第22题:
Estimating schedule activity costs involves developing an (1) of the cost of theresources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. for example, in most application areas, additionalwork during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. the cost estimating process considers whether the expected savings can offset the cost of the additional design work. cost estimates are generally expressed in units of (2) to facilitate comparisons both within and across projects.the (3) describes important information about project requirement that is considered during cost estimating. 空白(3)处填()
第23题:
The path cost can be changed for an interface using the spanning-tree cost command
The path cost can be changed for an interface using the stp path-cost command
The SPT default path cost depends on the interface speed
The STP default path cost is similar for all interface